Skip to main content

Tag: Mote Marine

Commission considers removing walls from City Pier building

ANNA MARIA – City commissioners will soon be asked to reach consensus regarding the possibility of transforming the fully-enclosed City Pier building previously occupied by Mote Marine into an open-air space that utilizes “hurricane-proof” retractable sliding doors on at least two sides. 

Mayor Mark Short presented the open-air building shell scenario during the Thursday, March 5 ,Anna Maria City Commission workshop. On Thursday, March 12, at 1 p.m., Short will seek commission consensus to move forward with getting price quotes to replace some of the pier building walls with sliding doors. If supported by the commission, the price quotes would be sought through the city’s request for proposals (RFP) process. 

During the March 12 meeting, the commission will not be asked to decide whether the larger pier building previously occupied by Mote Marine will be utilized as a full-service restaurant, an open-air cantina or something else. 

MAYOR’S PRESENTATION

Before discussing the future configuration and future use of the vacated T-end pier building, Short began the March 5 discussion by providing updates on the state of the City Pier walkway reconstruction, repair and remediation project. 

Short said the total estimated cost of the pier project remains in the $7.1 million to $7.8 million range he previously estimated. He said, to date the city has spent slightly more than $2 million on the pier project and that includes engineering and design work, and the demolition work and debris removal needed for the pier walkway that was destroyed by Hurricane Milton in 2024. 

Short included in his presentation a cost estimate that includes $700,000-$900,000 to repair the T-end platform decking and buildings, the bathrooms, the lighting and more. The total estimated cost also includes $500,000-$600,000 to install new electrical, water, sewage and natural gas lines and connections.

Regarding the project funding, Short mentioned the $1.25 million state appropriation approved last year, up to $2 million in recently approved county funds and FEMA’s recently stated obligation to provide $3.6 million in future reimbursements for the hurricane-related pier project. Short said the state, county and federal funding obligations total $6.84 million and the city will cover any remaining and additional costs. 

FUTURE USE

Short noted current pier tenant Brian Seymour still has 15 months remaining on his five-year lease that was originally scheduled to be extended or allowed to terminate on Dec. 31, 2025. If Seymour decides to resume his pier-based City Pier Grill & Bait Shop operations in the smaller pier building, the remaining 15 months of the lease would resume when that space can be occupied and his business operations can resume. 

Seymour also has the option to extend his existing lease for five more years. Seymour previously expressed interest in renegotiating his lease to include the larger pier building.

The smaller pier building leased to Brian Seymour is outlined in blue, the public restrooms are outlined in orange and the larger pier building previously occupied by Mote Marine is outlined in green. – City of Anna Maria | Submitted

Short said the city has the option to expand Seymour’s current lease to include the larger pier building, but the city is not obligated to do so. 

Short said he anticipates the city issuing a request for proposals (RFP) seeking multiple bids for the future use of the larger pier building. 

Short told the commissioners he sees two viable options for the larger pier building: Keep the enclosed structure or issue an RFP seeking construction company bids to remove some walls and replace them with sliders. And after that, the commission would later determine the specific use for the open-air space.

Mayor Mark Short likes the flexibility provided by the open-air pier building scenario. – Joe Hendricks | Sun

Short said the open-air scenario would create an additional 96 seats at the T-end of the pier, but that scenario does not assume a full-service, sit-down restaurant operating in that space.

Commissioner Charlie Salem asked if the existing City Pier Grill building could provide the adequate kitchen space needed for the open-air scenario. Short said that might be a possibility. 

Short said pursuing the open-air option might delay the reopening of the pier. 

Short said an enclosed restaurant space would provide 50 seats for restaurant patrons but would not provide any additional seating space for Gulf Islands Ferry passengers who aren’t eating or drinking in the establishment. 

Short said installing sliders for an open-area scenario might take the $700,000-$900,000 he estimated for the T-end of the pier closer to the upper end of that price range, but he doesn’t expect the slider installations would exceed his current $900,000 top end estimate. 

Salem said the city needs to consider the immediate needs of the next pier building tenant while also being able to accommodate the needs of a different tenant 30 years from now.

Commissioner Gary McMullen said the sliders would provide more options as to how the pier building can be used and he’s in favor of opening that space up with sliders. 

Short said the commission should proceed under the assumption that there will be a county-funded Gulf Island Ferry landing attached to the City Pier and that needs to be factored into the commission’s decision-making process. 

“The county is pretty adamant about that ferry,” McMullen added. 

Salem said the county’s engineers might be able to incorporate some passenger seating in their ferry landing design. Short said that’s possible, but the county hasn’t provided any recent ferry landing updates. 

Short noted the county’s ferry landing design will require city commission approval. 

Commissioner Kathy Morgan-Johnson said she’d like to know how the pier building is going to be used before deciding whether to open it up by installing sliders. “And then design around that,” she said. 

Commissioner Kathy Morgan-Johnson thinks the future use of the pier building should be determined first. – Joe Hendricks | Sun

Salem said the city should provide the building shell it desires and then it’s up to the next tenant to figure out how to utilize that leased space.

Short said issuing an RFP for the building modifications might delay the reopening of the pier. He noted the RFP process generally takes 60-90 days from the issuance of the RFP to the selection of the preferred bidder. Short said replacing walls with sliders provides the city greater flexibility regarding the future use of that pier space. 

PUBLIC INPUT

During public input, Anna Maria resident Ray Hyer said the existing building shell should be left as is and the next tenant can plan accordingly. Hyer said he’s remodeled 13 houses and it’s always more complicated and more expensive than originally expected.

Seymour noted sliders are already in place along the one wall that served as the main entrance to the Mote Marine facility. Seymour said he would reserve his opinion as to whether the building should remain enclosed or be opened up, but he said the building is more valuable to the city if the tenant is provided dedicated seating space for a restaurant.

City Pier Grill operator Brian Seymour is concerned about further delays with the pier reopening. – Joe Hendricks | Sun

Anna Maria resident Barb Ehern said she likes the idea of people being able to use that pier space without being obliged to patronize the restaurant. She said the slider scenario would better serve city residents, the public and the ferry passengers. 

“We should decide what we want there before we spend all this money opening it up and then maybe we change our mind,” Morgan-Johnson reiterated.

Short said taking no action on the building shell would default back to the current enclosed, four-wall scenario. 

POST-MEETING THOUGHTS 

After the meeting, Seymour said he was happy to hear Morgan-Johnson say she wanted the commission to determine the use of the building before determining whether to open it up by installing sliders. 

Seymour said he’s concerned about the multiple RFP processes needed for the slider scenario further delaying the pier’s reopening.

He said the enclosed versus open-air scenarios will impact his decision on whether to resume his pier-based business operations.

“It’s two vastly different uses. One is a full-service restaurant on that side, with dedicated seating or one that’s very limited, with us using our existing space,” he said.

Seymour said he doesn’t think the 250-square-foot building that served as his City Pier Grill kitchen and food preparation space could adequately accommodate a larger restaurant.

He noted 77% of the people who responded to the city’s survey supported a full-service restaurant in the larger pier building and the majority of the Facebook comments he’s seen are in agreement.

Seymour thinks both pier buildings should be leased to the same tenant – as was the case when previous pier tenant Mario Schoenfelder leased both pier buildings for his restaurant and bait shop operations prior to Hurricane Irma’s arrival in 2017. Seymour said he’ll be disappointed if the mayor and commission decide to issue an RFP to open the larger building up without first meeting with him as the current pier tenant.

Future use of the City Pier buildings discussed 

 ANNA MARIA – The city hosted a town hall meeting regarding the future use of the City Pier building previously occupied by Mote Marine. 

Many who spoke during Tuesday, Jan. 27, meeting would like to see a full-service, sit-down restaurant on the pier. 

Mayor Mark Short scheduled the town hall meeting because he and the city commission wanted to hear what the public wants to see in the hurricane-impacted pier space vacated by Mote Marine. The building previously occupied by Mote Marine is the larger of the two city-owned buildings at the T-end of the pier. 

Anna Maria General Store owner/operator Brian Seymour and his business partners hold the lease on the smaller pier building from which they operated The City Pier Grill & Bait Shop from 2020 until Hurricane Milton ripped away the City Pier walkway in October 2024. The smaller pier building does not provide space for indoor seating. 

The City Pier Grill & Bait Shop operated from the smaller building from 2020 until the 2024 hurricanes struck. – Joe Hendricks | Sun

Before opening the town hall meeting up for public input, Mayor Mark Short said the pier replacement project that includes the construction of a new pier walkway and also includes repairs and remediation to the hurricane-impacted pier buildings and the replacement of utility lines and other infrastructure needs is now estimated cost between $7.1 million to $7.8 million. 

Short said that cost estimate doesn’t include the higher amperage power supply and the interior buildout that might be needed to operate a larger, full-service restaurant on the pier.

Short said his goal is to have the City Pier fully reopened at some point this fall.

Short said the county’s desire to install a Gulf Islands Ferry landing alongside the new City Pier walkway to accommodate the larger, partially enclosed 96-passenger ferry boat (Manatee Belle) the county could result in 90 passengers getting off the boat and 90 more passengers waiting to board the boat at the same time and that too would impact the future use of the pier buildings.

Short said he doesn’t want the City Pier to become exclusively used as a staging area for the county’s ferry passengers and he wants the pier to remain available to all users. 

Commissioner John Lynch said he believes the mayor and commission are embracing the county’s ferry service but there are “critical issues” that need to be addressed regarding the flow of all those additional people on the pier.

Short said he and the commission need to have a pretty good sense of how the pier buildings will be used before the pier walkway is fully constructed and completed by March 31. 

PUBLIC INPUT

Short asked that one town hall attendee at a time come forward at a time to suggest a potential use of the pier building to be discussed before another potential use was suggested. 

Speaking first, Anna Maria resident Amir Banaly said he’d like to see the larger pier building used as a coffee shop. 

“I think it’s very simple to accommodate and accomplish without any changes,” he said.

Anna Maria resident Janis Ian suggested a coffee stand with one or two New York City-style hotdog carts. 

“I think a hot dog cart on the pier would look cool,” Ian said.

Janis Ian shared her views on the future use of the larger pier building. – Joe Hendricks | Sun

She also encouraged the mayor and commission not to be held hostage by the county regarding the impacts a larger ferry boat would have on the pier operations.

Seymour suggested an operation similar to what former pier tenant Mario Schoenfelder did until Hurricane Irma closed the previous pier in 2017. Schoenfelder operated the City Pier Restaurant in the larger pier building and a bait shop and draft beer bar in the smaller building. 

Seymour said he and his business partners still have 15 months remaining on the hurricane-suspended lease that was scheduled to expire on Dec. 31, 2025. He said he and his partners also have the option to lease the pier for five more years beyond the remaining 15 months that will resume when the pier reopens. 

Brian Seymour expressed interest in leasing both city-owned pier buildings. – Joe Hendricks | Sun

Seymour said it may not make sense for him to resume his City Pier Grill operations in the small building only. He said he would be interested in leasing both pier buildings to operate a sit-down restaurant in the large building and use the smaller building as a bait shop that serves draft pier and provides additional storage space. 

Anna Maria resident Cory Jackson said he’s president of Anna Maria Beach Cottages and his rental guests tell him they would like a to see a sit-down restaurant on the pier again.

“I think it’s very critical that we have a restaurant,” Jackson said.

Anna Maria resident and planning and zoning board member Jeff Rodencal suggested revisiting a previously discarded idea to install a stand-alone ferry landing between the pier walkway and the Lake La Vista jetty and he encouraged the commission to consider not landing all the ferry passengers on the City Pier at all. 

No decisions were made during the town hall meeting and the future use of the City Pier buildings will remain an ongoing topic of conversation for the mayor and commission until some decisions are made.

City Pier buildings emptied

City Pier buildings emptied

ANNA MARIA – The hurricane-damaged contents of the city-owned buildings at the T-end of the City Pier have been removed.

The content removal is the first step of cleaning, remedi­ating and repairing the pier spaces leased to The City Pier Grill and the Mote Marine Science Education & Outreach Center.

During the Oct. 23 city commission meeting, Mayor Mark Short provided a recap of the content removal efforts that began on Oct. 21 using a barge, as the pier is otherwise inacces­sible without its walkway. Short and city staff provided com­missioners with photos of the two interior pier spaces as and after the contents and some of the hurricane-related mud and muck were removed. Short said mold is present in the buildings as well and that will also have to be remediated.

During a previous city commission meeting, Short said Mote Marine had not yet informed him as to whether or not the Mote facility will return to the pier space provided rent-free by the city. Earlier this year, City Pier Grill operator Brian Seymour said he and his business partners hope to return to the pier if an extended lease can be negotiated to include some additional modifications they are requesting.

During the Oct. 23 meeting, Short said the repair and remediation work for the T-end buildings will occur simultaneously with the construction of the new City Pier walkway to be built by Tampa Bay Marine Inc.

Short said he was told the first solid concrete pilings are expected to arrive on Nov. 3, weather permitting, and the first batch of pilings will be installed and then tested upon delivery.

City Pier buildings emptied
The exhibit tanks and other contents were removed from the Mote Marine building. – City of Anna Maria | Submitted

Commissioner Charlie Salem asked if any of the pier building contents were salvageable. Short said that’s up to the pier tenants to determine and the contents were delivered by barge to a nearby marina for the tenants to inspect and relocate or discard.

Salem asked if the pier buildings remain structurally sound. Short said he didn’t see any signs of structural unsoundness but the drywall, ceiling tiles and some of the other interior elements require replacement.

In response to another question from Salem, Short said nothing he saw during his Oct. 21 visit led him to believe the previous estimate of approximately $800,000 to remediate and repair the T-end buildings will increase.

Short recently told com­missioners the total City Pier replacement project cost is now expected to be between $6.2 million and $6.9 million, including the $4.64 million walkway replacement contract with Tampa Bay Marine.

City, county officials discuss pier replacement, ferry landing

City, county officials discuss pier replacement, ferry landing

ANNA MARIA – City officials’ desire to rebuild the hurricane-damaged City Pier walkway and Manatee County officials’ desire to install a ferry landing at the pier are financially and philosophically intertwined.

The city needs county funds to help replace the pier walkway weakened by Hurricane Helene and mostly destroyed by Hurricane Milton. The pier wasn’t insured and the city doesn’t have enough money to self-fund the project.

The county needs the City Pier to serve as the Anna Maria stop for the larger ferry boat that will join the Gulf Islands Ferry fleet later this year. The county’s long-term goal is to use the larger ferry boat to transport passengers between the City Pier and downtown Bradenton and use the two pontoon boats as “Island hoppers’ that travel between Anna Maria, Bradenton Beach and the South Coquina boat ramp – and potentially Holmes Beach. The county also plans to include a ferry stop at the Cortez Marina in Cortez when the county-owned marina is built.

The Gulf Islands Ferry service currently runs between the Riverwalk Day Dock in downtown Bradenton and the Bradenton Beach Pier in Bradenton Beach.

City, county officials discuss pier replacement, ferry landing
Manatee County wants to install a ferry landing alongside the City Pier walkway when the missing walkway is replaced. – Joe Hendricks | Sun

On June 16, Anna Maria Mayor Mark Short appeared before the Manatee County Tourist Development Council (TDC), which recommends county commission approval for the city to use up to $2 million of tourist development tax revenues for the City Pier project.

City/county meeting

On June 18, Short, city commissioners Charlie Salem, Chris Arendt and Kathy Morgan-Johnson and City Clerk Amber LaRowe met with County Commission Chair George Kruse, County Administrator Charlie Bishop and other county staff members. County commissioners Tal Siddique and Carol Ann Felts participated by phone. The city and county officials discussed several topics but first and foremost were the related pier and ferry landing projects.

City, county officials discuss pier replacement, ferry landing
Mayor Mark Short presented the city’s pier-related funding needs to county commissioners and county staff. – Manatee County/YouTube | Submitted

For cost saving purposes, the current pier walkway that opened in 2020 was built atop hollow concrete pilings and a wooden support structure. The new pier walkway will be built atop solid concrete pilings and a concrete support structure similar to the T-end of the pier that survived the 2024 hurricanes.

Short estimates the pier walkway replacement will cost between $7 million and $9 million and hopefully be completed by October 2026. He said the city’s pier walkway replacement project and the county’s ferry landing installation must remain separate projects because the emergency permit received from the U.S. Army Corps of Engineers requires the new walkway to be built in exactly the same footprint.

The city will know by July 1 whether Gov. Ron DeSantis vetoes the city’s pier-related $1.25 million state appropriation request. Those state funds would be available on Oct. 1 if not vetoed. The city anticipates receiving around $4 mil­lion in pier-related FEMA reimbursements but those federal funds aren’t guar­anteed and Short doesn’t know if or when the city will receive them.

Short said the city already spent $223,000 on the pier project. He estimates the city will spend another $1.1 million between now and September, including $239,500 for the demoli­tion of the remaining pier walkway and $800,000 to repair and remediate the T-end pier buildings that sustained flood damage but remain structurally sound. Short estimates the city will need $3.1 million in 2025 and another $4.1 million in 2026 for the pier project.

Kruse asked Short who is responsible for restoring the T-end pier buildings oc­cupied by Mote Marine and the City Pier Grill. Short said the city will repair and remediate the city-owned pier buildings and the pier tenants are responsible for replacing their damaged equipment and contents.

Kruse asked Short if he expects Mote Marine to return to the pier.

“If that goes away, it’s not the same,” Kruse said.

Short said Mote personnel recently visited the pier by boat and are assessing Mote’s future plans.

Bradenton Area Conven­tion and Visitors Bureau Executive Director Elliott Falcione said the Mote space could be used as a ferry passenger waiting area if Mote doesn’t return. Kruse said he’d like to see that space used for some­thing more than a waiting area.

Falcione said Natural Resources Director Charlie Hunsicker estimates the City Pier ferry landing will cost the county an additional $1 million to $1.5 million. Falcione also said Manatee County Area Transit (MCAT) will assume oversight of the county-contracted ferry service on Oct. 1 and the visitors bureau will continue marketing and promoting the ferry service it currently oversees.

Kruse insights

Kruse expects county commissioners to vote on the $2 million TDC recom­mendation on July 29.

He noted the $4 million in potential FEMA funds equates to about half the estimated pier replacement costs.

“It could be 18 months before you know if you’re even going to get it and another three years before you actually get it,” Kruse said of the FEMA funds.

City, county officials discuss pier replacement, ferry landing
County Commission Chair George Kruse supports using county funds to help cover the pier walkway replacement costs. – Manatee County/YouTube | Submitted

Speaking for himself, and not the county commission, Kruse said the county may need to front the city the additional money needed to complete the project, with the city later reimbursing the county using FEMA funds or other funding sources.

“This has to be rebuilt,” Kruse said. “I don’t think there’s any alternative. It’s critical to our tourism, it’s critical to our residents and we’ve got great amenities out there. We need the landing space. We want people to go to Mote. We want people to go to the grill. We want people to use that pier.”

He also mentioned the economic impact of ferry passengers visiting the restaurants and businesses within walking distance of the pier, and beyond.

City, county officials discuss pier replacement, ferry landing
Manatee County wants to install a new ferry landing alongside the Anna Maria City Pier. – Manatee County | Submitted

Kruse suggested Mote Marine and City Pier Grill representatives meet with city and county officials for an all-inclusive discus­sion. He also said city and county staff need to create a funding proposal.

Kruse mentioned the hurricane-related line of credit the county secured, the county’s reserve funds and the county’s tourist development tax revenues as potential funding sources.

“I don’t think this is a question of should we do it,” Kruse said. “I think it’s a question of where’s the money coming from in the short term and where’s the money coming from in the long term? It’s still taxpayer money.”

“We understand and we appreciate that,” Short said.

Related coverage:
Mayor seeks TDC support for pier replacement project
Manatee County, Bradenton Beach officials discuss ferry options
City Pier Grill operators hope to renegotiate lease
City commission narrows ferry landing options

Water Quality Concerns

Water quality concerns persist

ANNA MARIA ISLAND – Water quality concerns persist as the city of Bradenton continues to discharge partially-treated sewage into the Manatee River.

During and immediately after Tropical Storm Debby in early August, the city discharged an estimated 25 million gallons of untreated and partially-treated sewage and wastewater into the Manatee River. According to reports posted at the city’s website, the sewage discharge remained ongoing as of Sept. 6, with more than 1,000 gallons per day being discharged into the river.

During and after the storm, which became a hurricane after it passed the Island, the city of Sarasota discharged an estimated 18 million gallons of sewage and wastewater into Sarasota Bay.

On Sept. 6, the Florida Department of Health (FDOH) issued water quality advisories for Bayfront Park in Anna Maria and south Palma Sola Bay in west Bradenton. According to the advisory, tests on Sept. 3 and Sept. 5 indicated the water quality did not meet recreational water quality criteria for enterococcus (fecal) bacteria recommended by FDOH, which “advises against any water-related activi­ties at these locations due to an increased risk of illness in swimmers.”

After Debby, Mote Marine Laboratory scientists recorded a significant spike in Sarasota Bay concentrations of nitrate and ammonia, which can serve as an increased source of nutrients for aquatic bacteria and algae such as red tide.

Red tide was observed at background concentrations in one sample from Manatee County, at the Rod and Reel Pier in Anna Maria, the Florida Fish and Wildlife Conservation Commission reported on Sept. 6.

Related coverage:
Sewage discharge continues

43 million gallons of sewage discharged during Debby

Gulf Islands Ferry service begins

Gulf Islands Ferry service begins

ANNA MARIA – Making its maiden voyage for the Gulf Islands Ferry service on a cold and windy day, the Miss Anna Maria ferry boat docked at the Anna Maria City Pier at approxi­mately 9:45 a.m. Sunday morning.

Carrying six passengers who trav­eled down the Manatee River from the Riverwalk Day Dock in downtown Bradenton, the Miss Anna Maria was the first Manatee County-funded Gulf Islands Ferry boat to arrive at the City Pier carrying paying passengers.

Gulf Islands Ferry service begins
Miss Anna Maria approached the City Pier after traveling down the Manatee River. – Joe Hendricks | Sun

Phil Quesnel captained Miss Anna Maria, assisted by crew member Mike Pollard, and the wind and waves made docking a challenge. After three unsuccessful attempts to dock nose-first, Quesnel and Pollard decided to pull up to the pier with the port side of the boat parallel to the landing area at the T-end of the pier.

Gulf Islands Ferry service begins
The wind and waves made docking nose-first difficult. – Joe Hendricks | Sun

Gulf Islands Ferry service begins
Miss Anna Maria eventually docked with the port side parallel to the pier. – Joe Hendricks | Sun

Eight-year-old Marlon Haoui was the first passenger off the ferry, accompa­nied by his parents, Bryan and Annslie Haoui, and their friend, Holly Mayotte.

When asked how it felt to be the first ferry passenger to set foot on the pier, Marlon said, “Good.”

When asked if it was cold on the river, he said, “Very.”

He was then asked what he planned to do in Anna Maria.

“We’re gonna go into the aquarium,” he said in reference to the Mote Marine Science Education & Outreach Center located on the City Pier.

“And then we’re going to get break­fast,” Annslie said.

“We figured this was historic, the first ferry ride from Bradenton to the Island, so let’s be the first ones to do it. We were looking forward to it,” Bryan said.

“We bought our tickets on Friday,” Annslie said, noting that she and Mayotte are teachers at the Team Success charter school.

“It was beautiful. We went right by our homes and up the river,” Mayotte said of their morning ride.

Gulf Islands Ferry service begins
Some ferry passengers planned to visit the pier-based Mote Marine Science Education & Outreach Center. – Joe Hendricks | Sun

When asked about the boating conditions, Pollard said, “It was a little rougher than we would’ve thought. We’re getting 2-3-foot swells out there. Hopefully, as the day goes on, it’ll settle down.”

Pollard said the wind, waves and other conditions determine the best way to bring the boat in to dock.

“That dictates whether you come in nose-first, port side or starboard side. Right now, it’s better to come in on the port side,” he said.

Quesnel previously captained charter boats in the Long Island, New York area.

“We’ve done this a few times as practice, but today was probably the roughest day,” he said in regard to docking at the City Pier.

Gulf Islands Ferry service begins
Kristen Deevy and her friends, Sue and Bob, were among the first five passengers to make the trip from the City Pier to downtown Bradenton. – Joe Hendricks | Sun

Five new passengers boarded Miss Anna Maria for the first return trip from the City Pier to downtown Bradenton. Visting from Colorado, Kristen Deevy and her friends, Sue and Bob, planned to eat brunch in downtown Bradenton and explore the downtown area on foot.

Gulf Islands Ferry service begins
Five passengers boarded the Miss Anna Maria for its first return trip to downtown Bradenton. – Joe Hendricks | Sun

According to Bradenton Area Con­vention and Visitors Bureau Marketing Director Kolby Gayson, 12 passengers booked passage on the Downtown Duchess for the ferry service’s second Sunday morning voyage to the City Pier.

Gulf Islands Ferry service begins
The passengers settled in for their ferry ride to downtown Bradenton. – Joe Hendricks | Sun

Weather permitting, Miss Anna Maria and her sister ship, Downtown Duchess, were to continue making hourly trips between downtown Bradenton and Anna Maria until 9 p.m. To establish consistency of service, the hourly ferry trips were to be made with or without passengers onboard.

The now-active Gulf Islands Ferry service will operate Fridays, Saturdays and Sundays from 9 a.m. to 9 p.m., weather permitting. The ferry service will also travel to the Bradenton Beach Pier once some needed docking modifications are completed there.

Gulf Islands Ferry service begins
At approximately 10 a.m., Miss Anna Maria headed back to downtown Bradenton. – Joe Hendricks | Sun

The round-trip fare for adults 18 and older is $10 and a one-way trip is $6. The round-trip fare for seniors, active military members and youths aged 4 to 18 is $6 and a one-way trip is $4. Children 3 and younger ride free. Tickets can be purchased in advance at www.gulfcoastwatertaxi.com.

Loggerheads released after recovering from red tide

Loggerheads released after recovering from red tide

ANNA MARIA – In a cooperative effort between Mote Marine Laboratory and The Florida Aquarium, two loggerhead sea turtles were released at Bayfront Park on May 30 after months of care and rehabilitation for the effects of red tide toxin.

“We are proud to collaborate with The Florida Aquarium in our shared mission to rescue and rehabilitate sea turtles,” Mote’s Rehabilitation and Medical Care Coordinator Lynne Byrd said in a press release. “By combining our expertise and resources, we can provide these magnificent creatures with the best possible care, ensuring their recovery and return to the big blue.”

The two rescued loggerhead sea turtles were nicknamed Valerie and Mahomes. Valerie was discovered floating nearshore off Longboat Key on Feb. 21. She appeared to have been affected by toxins from red tide, a waterborne algae that also can affect human respiration. She was transported to Mote’s Sea Turtle Rehabilitation Hospital in Sarasota and began receiving injectable antibiotics and subcutaneous fluids until symptoms improved.

When Valerie arrived at the hospital, Mote scientists found that she already had a flipper tag and a passive integrated transponder (PIT) tag. The PIT tag, placed by Mote’s Sea Turtle Conservation & Research Program in 2019, gave the turtle a unique barcode identification number that allowed scientists to gain valuable insights into her migratory patterns, growth rates, survival and reproductive output, according to Mote.
Mahomes was found washed ashore off Casey Key Road in Sarasota County and also showed symptoms of red tide toxicity.

Initially admitted to Mote’s Sea Turtle Rehabilitation Hospital on Feb. 13, Mahomes was later transferred to The Florida Aquarium Turtle Rehabilitation Center on Feb. 24 to better prepare Mote for what they anticipated to be high numbers of incoming sea turtle patients affected by toxic red tide exposure.

Mahomes received antibiotics and supportive care during the course of rehabilitation to help rid the sea turtle’s body of toxins.

Before the release, Mahomes was outfitted with a satellite tag by The Florida Aquarium and the Sea Turtle Conservancy.

“These tags provide critically important information about diving, feeding, migratory and activity patterns all while recording corresponding environmental data such as water temperatures. This data will help better understand the patient’s behavior after reintroduction and provides key insight for future rehabilitation and conservation efforts,” according to Mote.

Following their months of care, the loggerheads successfully cleared all health assessments mandated by wildlife officials for release.
“Every turtle matters, as they serve as ambassadors for the critical need to protect and conserve these creatures and the habitats they rely on,” Byrd said in the release. “Every rehabilitated sea turtle is a symbol of hope for the future of our oceans.”

Within Sarasota or Manatee county waters, if you see a stranded or dead sea turtle, dolphin or whale, please call Mote’s Stranding Investigations Program, a 24-hour response service, at 941-988-0212.

If you see a stranded or dead manatee anywhere in state waters or a stranded or dead sea turtle, dolphin or whale outside of Sarasota or Manatee counties, please call the FWC Wildlife Alert hotline at 888-404-FWCC (3922).

Mote Marine facility opening May 5

Mote Marine facility opening May 5

ANNA MARIA – The grand opening and ribbon-cutting ceremony for the Mote Marine education outreach center on the City Pier remains on track for Friday, May 5.

The ceremony will begin at 10 a.m. in City Pier Park, across the street from the pier, and be followed by a ribbon-cutting ceremony at the pier entrance.

During the April 13 city commission meeting, Anna Maria Mayor Dan Murphy said invitations were sent to Anna Maria city commissioners and other city and county officials.

Murphy expects the ceremony to last approximately 45 minutes. After the mayor’s introductory remarks, Mote Marine President and CEO Dr. Michael Crosby will speak. Some of the attending city and county officials may also make brief remarks.

Portions of Pine Avenue, North Bay Boulevard and South Bay Boulevard will be closed during the ceremony.

The grand opening ceremony is open to the public and the Mote Marine education outreach center will open to the public right after the ribbon-cutting ceremony. Featuring live and virtual marine life exhibits, the outreach center will then be open daily at no cost to the public.

At the recommendation of the Manatee County Tourist Development Council, the Manatee County Commission provided $500,000 in county funds for the interior buildout of the city building and the installation of the Mote Marine exhibits. Mote Marine is leasing the city building rent-free but will operate and staff the outreach center at its own expense.

“This has been a long, long, long, long, long time coming. We’re finally here,” Murphy said. “We’re at the cusp of opening it up and I’m really excited. I think it’s going to bring a lot to the city in terms of education. When we pursued this, it was about awareness and education.”

Murphy referenced the commission discussions and public debate that ensued in 2020 and 2021 and pertained to whether the larger of the two city-owned pier buildings should be leased to a full-service restaurant operator or be used for some other purpose. After multiple efforts to secure a restaurant operator fell short, the commission majority decided to pursue the Mote Marine facility instead.

“Do we have hamburgers or do we have knowledge? We opted for knowledge,” Murphy said of that decision-making process.

Commissioner Robert Kingan noted the city actually got both because the smaller pier building is already leased to the operators of the City Pier Grill & Bait Shop.

Kingan said he visited the pier facility the previous day and saw workers installing the backgrounds and displays associated with the live and virtual exhibits.

“I think it’s going to be a resounding success,” Kingan said.

“It’s all about public awareness and knowledge and research. The pier is the jewel of this city and has been for over 100 years. We’re dedicating it to science and research and knowledge about the environment and clean water,” Murphy said.

Commissioner Jon Crane said, “I, for one, am absolutely thrilled.”

“It’s exciting for it to finally be open,” Commissioner Deanie Sebring added.

Mote receives another extension for pier facility

Mote receives another extension for pier facility

ANNA MARIA – Mote Marine Laboratory was given an additional two weeks to obtain a city-issued certificate of occupancy for the education outreach center being installed on the City Pier.

On March 9, Anna Maria City Commissioners voted 4-1 in favor of granting the two-week extension. Commission Chair Mark Short opposed the extension. Mote now has until March 24 to obtain from the city’s building official a temporary or regular certificate of occupancy.

The discussion began with Mayor Dan Murphy stating that March 10 was the deadline for Mote to apply for a certificate, according to a lease addendum the city and Mote agreed to on April 29, 2022. The addendum gave Mote an additional year to complete the interior buildout of the city-owned building and the installation of the marine exhibits that were originally supposed to be completed by March 2022.

Mote receives another extension for pier facility
Kevin Cooper represented Mote Marine at the March 9 city commission meeting. – Joe Hendricks | Sun

Vice President of Communications and Strategic Initiatives Kevin Cooper represented Mote Marine at the commission meeting and he acknowledged Mote was going to fall short of its March 10 deadline. He attributed the latest delays to supply chain shortages regarding the air conditioning system and also the Square D stainless steel electrical components required by the city. Cooper said the alternative air conditioning system also required some additional engineering.

Cooper thanked Anna Maria Building Official David Gilson for his assistance in securing a different air conditioning system and the non-Square D stainless steel electrical components that still meet the city’s requirements.

Cooper said the marine life requires an onsite acclimation period before the outreach center can open to the public. He said a temporary certificate of occupancy would allow the marine life, and the marine exhibits built offsite, to be transported to the pier building. It would also allow outreach center manager Jessica Rhodes to occupy the building while awaiting the final certificate of occupancy that’s needed before the outreach center can open to the public.

Cooper said the fire marshal is willing to sign off on the fire suppression component of a temporary certificate if the work completed by March 24 doesn’t warrant a regular certificate of occupancy.

Mote receives another extension for pier facility
Mote Marine’s education outreach center is now expected to open in late April. – Joe Hendricks | Sun

According to the 2022 lease addendum, the outreach center was supposed to open this month. Cooper said Mote now envisions a public opening in late April.

Questions posed

Short asked Cooper why Mote waited until the day before the certificate of occupancy was due before seeking an extension. Cooper said those conversations began about a month ago and a March 7 onsite meeting with Gilson confirmed the need for an extension.

Short said he visited the pier building on March 6 and saw construction workers “mudding” the drywall and the ceiling. Short said it looked like a lot of work was still needed. He asked Cooper how much of the $500,000 in county commission-approved tourist development tax revenues Mote had spent thus far. Cooper said Mote expects to exceed the $500,000 allotted by the county but he did not say by how much. Mote’s rent-free lease with the city requires Mote to absorb any additional startup costs beyond the $500,000 approved by the county. Cooper also noted Mote will staff the facility at its own expense, with volunteers assisting with ongoing staffing needs.

Mote receives another extension for pier facility
Mote Marine’s education outreach center is being installed in the pier building on the right. – Joe Hendricks | Sun

Short asked if Mote had submitted any invoices to the city seeking reimbursement for costs incurred thus far.

Murphy said the city received a $96,000 invoice that morning and City Clerk/Treasurer LeAnne would review it and forward it to the county. The county will reimburse the city and the city will reimburse Mote as the invoices are received.

Mote Marine’s City Pier plans reviewed

Mote Marine’s City Pier plans reviewed

ANNA MARIA – Building Official David Gilson and City Planner Ashley Austin presented their review of Mote Marine’s plans to install an educational outreach center on the Anna Maria City Pier to commissioners last week.

Mayor Dan Murphy received the latest plans from Mote Marine on Oct. 13. Gilson and Austin provided their analysis of the plans during the special city commission meeting held on Thursday, Oct. 20.

He said the purpose of the meeting was for Gilson and Austin to share their analysis of the plans, with a focus on two primary criteria – assessing whether the plans meet the city’s technical requirements and whether the proposed plans meet the city’s quality expectations for a project on city-owned property.

Mote’s educational outreach center will occupy the larger and currently vacant city-owned building at the T-end of the City Pier. The smaller pier building is occupied by the City Pier Grill & Bait Shop.

Murphy sought the commissioners’ initial thoughts and comments on the plans, saying that Gilson would send questions and comments to Mote representatives. The revised plans will then be presented to the commission, which will be asked to approve the plans and authorize the building permits needed for Mote to begin the interior buildout of the pier building and the installation of its marine life exhibits.

Gilson said if the plans had been submitted as a standard construction project, they’d be very close to being accepted, but with the city being the property owner, the permitting process is different.

Mote Marine’s City Pier plans reviewed
This illustration references Mote Marine’s exhibition gallery. – City of Anna Maria | Submitted

“The way the lease is written, the owner (the city) is going to have their fingers in this entire project. The lease puts us right in the thick of it and that’s going to be very helpful,” Gilson said.

Gilson recommended the city specify that Square D electrical breaker panels are used because city staff is familiar with that brand. He also requested additional information from Mote regarding the invertebrate touch tank exhibit that requires an electrical connection, specifically, who’s serving as Mote’s contracted electrical engineer.

Gilson said the plans include a blanket statement regarding the use of corrosion-resistant hardware. He recommends the plans specify that the screws, nuts, bolts and other hardware used will be made of stainless steel, similar to what was used for the construction of the pier and pier buildings.

The plans don’t specify which type of ceiling tiles will be used. Because of the saltwater exhibits to be contained inside the building, Gilson recommends using higher quality ceiling panels that resemble drywall and are more humidity resistant than normal ceiling tiles.

Austin said the installation of an educational outreach center that offers incidental souvenir sales in an already existing space is considered a tenant buildout rather than new construction, so setback restrictions and other construction criteria don’t apply. She noted the plans don’t address signs and said Mote will need to apply for a separate sign permit.

Mote Marine’s City Pier plans reviewed
This drawing is included in Mote Marine’s latest plans. – City of Anna Maria | Submitted

Commissioner Robert Kingan asked if the plans include a backup generator. Gilson said he didn’t see anything in the plans about a generator, but that he talked to someone at Mote who said battery backups would be used to keep the live exhibits oxygenated during a power outage. Gilson said the safety of the sea creatures is ultimately Mote’s responsibility.

Kingan asked if Mote had identified a specific contractor. Gilson said Mote has a contractor that they regularly work with but the plans and building permit applications have not yet been officially submitted to the city.

Commissioner Mark Short asked Murphy if the plans he received on Oct. 13 satisfy the deadlines the city commission established earlier this year when granting Mote a lengthy extension to complete the long-delayed project.

Murphy said the latest plans comply, and that the city will hold Mote Marine to the March 2023 completion and opening deadline the commission established earlier this year.

Mote Marine submits City Pier plans

Mote Marine submits City Pier plans

ANNA MARIA – Mote Marine met its Oct. 13 deadline to present the city with detailed plans for the marine education outreach center to be installed on the City Pier, averting the possibility of the city commission terminating the project.

Mayor Dan Murphy mentioned the plans during the Anna Maria City Com- mission’s Oct. 13 meeting, saying he picked up digital copies of the plans that morning and forwarded copies to the city commissioners about an hour before that afternoon’s commission meeting began. He also provided copies to the city’s building official and city planner.

Mote Marine submits City Pier plans
The plans received from Mote Marine include this architectural drawing. – city of Anna Maria | Submitted

The plans were created by Mote Marine’s contracted architect, Barron Schimberg. Murphy said the plans are technical in nature, contain a lot of verbiage and address architectural elements, electrical elements, fire suppression elements and more.

Murphy requested a special city commission meeting to be held on Thursday, Oct. 20 at 10 a.m., at which he and the commission will discuss three primary objectives.

The first objective is to receive the building official and city planner’s analysis of the plans. The second objective is to pro- vide the commissioners the opportunity to pose questions to the building official and city planner and to also relay any commission questions to Mote representatives. Murphy said it wasn’t necessary for Mote Marine representatives to attend the special meeting.

“This is our chance to review those plans collectively and put together our concerns, comments or questions both for our building official and for Mote,” he told the commission.

The third objective is to establish the timelines to move forward with the completion of the project. Murphy said this would include holding another meeting during which Mote representatives can directly respond to any lingering questions posed by the commissioners. Permitting and installation schedules must also be formulated for the completion of the pier-based Mote Marine facility.

The initial concept for the Mote Marine educational outreach center was first presented to city commissioners in February 2021. The commission later voted 4-1 to move forward with the outreach center as its preferred use for the vacant city-owned pier building. Commissioner Mark Short opposed that use of the city building for that purpose and expressed his preference that it be used for an open-air cantina or a full-service restaurant.

In response to ongoing planning delays experienced by Mote Marine, the city commission, on April 22, gave Mote until Oct. 13 to submit its completed plans for the facility or face the possibility of the project being terminated by the commission. During that meeting, the commission also established a March 1, 2023 deadline for the Mote facility to be completed and opened to the public.

Conceptual plans

During the April meeting, the commission also reached a majority consensus in support of the latest conceptual plans presented that day by Mote Marine representative Kevin Cooper. The conceptual plans Cooper presented were in the form of colored renderings that illustrated four live exhibits, with the centerpiece being an invertebrate touch exhibit that includes horseshoe crabs, starfish and other marine life.

Mote Marine submits City Pier plans
The Mote Marine facility will feature an invertebrate touch tank. – city of Anna Maria | Submitted

The mangrove exhibit will include a mangrove tree and marine species inhabiting the mangrove’s submerged root system. The grass flats exhibit will feature marine species found near the City Pier. A fourth exhibit will employ live cameras and a hydrophone to provide real-time sights and sounds of the marine life and environment underneath the City Pier.

Mote Marine submits City Pier plans
Presented in April, this rendering illustrates the conceptual plans for the Mote facility. – city of Anna Maria | Submitted

Additional interactive and educational exhibits will include microscopes, a game fish identification exhibit, a “Draw Alive” exhibit that allows visitors to create digital marine life images and an exhibit that allows visitors to create textured rubbings of fish and other marine life.

Funding

Using tourist development tax revenues, Manatee County will provide the city with $500,000 to cover the majority of the initial costs incurred during the installation of the Mote Marine facility. Mote Marine will cover any additional installation expenses. Mote Marine will not pay the city rent for the use of the pier building but will staff and operate the pier-based facility at its own expense. The city will cover the facility’s ongoing utility expenses.

Mote modifies pier facility proposal

Mote modifies pier facility proposal

Mote Marine Laboratory has provided the city with a new proposal for the interior layout of the marine educational outreach center to be installed on the City Pier.

The outreach center will be in the vacant, city-owned building at the T-end of the new pier.

After receiving Mote Marine’s latest proposal on Thursday, Jan. 27, Mayor Dan Murphy forwarded the document to city commissioners. During that evening’s commission meeting Murphy noted the commissioners had not yet had much time to review the new proposal, which will be discussed at a future meeting.

Mote modifies pier facility proposal
The pier space that will contain the Mote Marine facility was originally offered for lease to potential full-service restaurant operators. – Joe Hendricks | Sun

Mote’s new proposal features more digital and virtual exhibits. The previous plan included live exhibits containing smaller sport fish, schooling fish and a touch tank featuring urchins, starfish, sea cucumbers, horseshoe crabs and slipper lobsters.

Exhibits and features

The new proposal includes a “Fish Sounds” exhibit that would allow guests to activate recorded marine life sounds and compare those to real-life sounds heard live through an underwater microphone installed at the pier.

It also includes a live streaming video exhibit on the marine life under the pier, projecting real-life images on the exhibit walls. It also would have a mangrove column illustrating how these plants provide crucial habitat for young fish and other marine life.

Mote modifies pier facility proposal
This is the latest floor plan proposed by Mote Marine. – Mote Marine | Submitted

Another exhibit would help users identify and learn more about the fish they catch on the pier and elsewhere in Anna Maria.

Additional panels would explain Mote’s research efforts directly related to Anna Maria Island, including information on fisheries, sharks and rays, sea turtles, manatees and red tide.

According to the proposal, schooling fish, mangrove roots and other sea life will be set into the floor to “create a dynamic learning environment.”

The proposal includes a “Draw Alive” interactive exhibit that allows youngsters and adults to color a sea creature, place it on the scanner and watch it come to life on a video screen.

The latest proposal also includes an interactive microscope exhibit that projects microscope images onto a video monitor.

Mote modifies pier facility proposal
This rendering illustrates Mote Marine’s proposed “Draw Alive” and video exhibits. – Mote Marine | Submitted

When contacted later in the week, Murphy said commissioners will decide if they prefer the new proposal, the original proposal or a combination of the two. During a previous commission meeting, Murphy said Mote no longer anticipates completing its installation work in March as previously predicted.

On Tuesday, Feb. 1, the city posted the following message on its Facebook page: “Have you heard Mote Marine will open a learning center on the T-end of our City Pier? Here’s a quick update of where things stand: There are two conceptualized plans – one that includes tanks for live marine life, and one that doesn’t. Both options will be considered equally after the engineer and building official review the plans and make their recommendations. Either way, we’re very excited to welcome Mote to Anna Maria and look forward to seeing you all there soon.”

Mote modifies pier facility proposal
The Mote Marine facility will be located in the currently vacant pier building to the right. – Joe Hendricks | Sun

Decision still pending on clam, seagrass restoration funds

Decision still pending on clam, seagrass restoration funds

ANNA MARIA – A city commission decision on a $50,000 funding request for proposed clam and seagrass restoration projects has been further delayed as opponents voice concerns.

The additional delay is partially due to revisions made to the proposals that Ed Chiles and his associates previously presented to the city commission on Jan. 13, when Chiles and representatives from the Gulf Shellfish Institute, The Diatom Initiative and Sea & Shoreline requested $50,000 for the proposed restoration projects.

The money sought would come from the approximately $850,000 in American Rescue Plan (ARP) funds the city of Anna Maria will receive from the federal government. The city’s 2021-22 fiscal year budget earmarked $55,000 in ARP funds to address red tide/environmental issues.

The funding decision is also being delayed pending an appearance before the commission by 35-year Manatee County resident and retired marine ecologist Dr. Randy Edwards, who opposes the plan. Edwards will address the commission during the Thursday, Feb. 10 meeting that begins at 2 p.m.

On Jan. 13, Chiles told the commission a group of unnamed private donors would match dollar for dollar up to $50,000 in additional funds donated by the community at large. Chiles said this could turn a $50,000 effort into a $150,000 effort.

The group’s original proposal called for 20,000 southern hard and sunray venus clams to be placed in the Tampa Bay waters offshore of Anna Maria and in local canals. The proposal also calls for a seagrass restoration project in Bimini Bay – an interior body of water located in both Anna Maria and Holmes Beach.

Decision still pending on clam, seagrass restoration funds
Local restaurateur and businessman Ed Chiles, standing, is enthusiastic about using clams to improve water quality. – Joe Hendricks | Sun

Citing lingering concerns as to whether clams help remove red tide cells from the water, Commissioner Jon Crane requested the commission delay its funding decision until first hearing from Kevin Claridge regarding Mote Marine Laboratory’s red tide research and mitigation efforts. Claridge is vice president of Mote Marine’s sponsored research and coastal policy programs.

“I am told that clams and oysters do generally clean water, but there is no evidence that clams or oysters remediate red tide,” Crane said on Jan. 13.

He also questioned whether the red tide cells removed from the water by clams are redeposited into the water via the clams’ excrement.

On Wednesday, Jan. 26, Mayor Dan Murphy received a revised proposal from Diatom Initiative founder and clam hatchery operator Curt Hemmel. The proposal increases the number of clams from 20,000 southern hard and sunray venus clams to 1-2 million southern hard clams, with no sunray venus clams, which are often harvested for dining purposes.

Decision still pending on clam, seagrass restoration funds
Diatom Initiative founder Curt Hemmel has provided the city with a revised clam restoration proposal. – Joe Hendricks | Sun

Hemmel’s revised proposal was accompanied by a letter of support from Gulf Shellfish Institute Executive Director Stephen Hesterberg.

“It is empirically well supported that filter-feeding, bivalve shellfish improve water quality, support adjacent marine habitats and eliminate the organism that causes red tide. Although it is true that some nutrients delivered to the sediments are resuspended, a substantial amount of nitrogen can also be rendered inert by bacteria or utilized by beneficial submerged aquatic vegetation such as seagrass. Numerous peer-reviewed studies demonstrate that bivalves can facilitate seagrass production through improved water clarity and nutrient transfer,” Hesterberg stated in his letter.

Decision still pending on clam, seagrass restoration funds
Gulf Shellfish Institute Executive Director Stephen Hesterberg believes the proposed restoration programs would provide additional research opportunities. – Joe Hendricks | Sun

“The exciting technologies being developed at Mote Marine Laboratory, such as clay application and ozonation/cavitation/oxidation, should absolutely be included in our arsenal of means to mitigate red tide. However, it is important to clarify these methods are reactive to when red tide blooms arise, and do not prevent or address the root causes of harmful algal blooms. In other words, such tools fight a wildfire once it is raging, but do not lower the risk of one starting,” Hesterberg stated in his letter.

Mote presentation

When appearing before the city commission on Thursday, Jan. 27, Claridge provided an overview of the red tide research being conducted by Mote Marine and its research partners.

Decision still pending on clam, seagrass restoration funds
Mote Marine’s Kevin Claridge addressed the city commission on Jan. 27. – City of Anna Maria | Submitted

He said the potential red tide mitigation methods being researched include natural algaecides, ozonation, clay disbursement, UV light rays and more. Claridge said tiered testing of these potential mitigation strategies is taking place in inland test tanks before being introduced to the natural waters.

Claridge noted this research pertains to red tide mitigation rather than habitat and marine life restoration. He also noted Mote Marine is not directly involved in studying the effectiveness of clams and other bi-valves regarding their ability to filter out red tide cells.

Additional comments

Crane addressed a point raised in a letter he received from Edwards, who listed his past associations with Mote Marine, the U.S. Geological Survey and the University of South Florida. Crane asked if the 20,000 clams originally proposed would equate to a “drop in the bucket” in terms of addressing water quality issues.

In his letter, Edwards stated, “20,000 clams would filter an infinitesimally small volume of the bays. Their filtration effect would be so small, compared to the volume of water in the bays, to be totally insignificant and would have no meaningful positive impact. The question is what better could be done with the $50,000 by the city; it would be far better to invest it in reducing stormwater nitrogen runoff to the bay.”

Commission Chair Carol Carter noted Mote Marine is not seeking any project funding from the city and that Claridge appeared at the city’s request.

Carter noted both restoration projects propose restoration efforts in and offshore of Anna Maria and Holmes Beach. She suggested the group either seek some of the funding from the city of Holmes Beach or limit the scope of the restoration projects to Anna Maria. Carter also noted the city has not yet received a formal written proposal regarding a funding request and she recommended one be submitted. Murphy also recommended a more formal written proposal be submitted.

Anna Maria: The Year in Review

Anna Maria: The Year in Review

ANNA MARIA – The pending Reimagining Pine Avenue safety improvements and the pending Mote Educational Outreach Center were among the projects initiated in Anna Maria in 2021.

The year was also marked by the return of several community events that were canceled in 2020 due to the coronavirus pandemic.

January

In early January, a fishing trawler sank offshore of Anna Maria and littered the Bean Point beach area with debris that required a significant clean-up effort by the city and Manatee County.

Anna Maria: The Year in Review
This was among the shipwreck debris that washed ashore in Anna Maria in January 2021. – Kristin Swain | Sun

A Bradenton Beach resident sustained bruises and minor injuries after being struck by a car while crossing the street at the Gulf Drive/Spring Avenue intersection.

A large and long-abandoned sunken sailboat was finally removed from the waters near the City Pier.

February

The COVID Ribbon Memorial of Florida was unveiled along the beach near the Sandbar restaurant. Created by Anna Maria resident, photographer and artist Cathy Tobias and some of her friends, the colorful art installation consisted of a string of brightly colored plastic ribbons that stretched more than 250 yards and represented each of the more than 27,000 Florida residents who had died of COVID-19 at that point.

Anna Maria: The Year in Review
The COVID Ribbon Memorial of Florida was unveiled on the beach in February. – Joe Hendricks | Sun

The city commission adopted a new ordinance that prohibits hoverboards, OneWheels, scooters, skateboards and bicycles on Anna Maria’s beaches and inside city parks – with an exception made for bicycles in city parks.

The commission voted 4-1 in favor of Mote Marine’s proposed educational outreach center occupying the vacant City Pier building, originally built in 2020 with the expectation of being leased to the operator of a full-service restaurant.

Anna Maria: The Year in Review
This rendering illustrates the preliminary concept for the Mote Educational Outreach Center. – Mote Marine | Submitted

Longtime Anna Maria resident Margaret Jenkins passed away at the age of 90.

March

Anna Maria resident Jennifer Kaleta addressed the city commission regarding the notification she received from the city informing her that her outdoor chicken coop violated city ordinances and had to be removed, much to the chagrin of her and her children.

April

Commission Chair Carol Carter, Mayor Dan Murphy and lobbyist Chip Case played key roles in defeating the Florida Legislature’s latest attempts to preempt vacation rental regulations to the state. Utilizing the city-owned Home Rule Florida website, www.homerulefl.com, the city and its supporters helped defeat Senate Bill 522 and House Bill 219.

May

The commission authorized a $50,274 consulting fee for the Reimagining Pine Avenue study that later produced several recommended pedestrian and bicycle safety improvements to be made in 2022, including new sidewalks and new and improved crosswalks.

Anna Maria: The Year in Review
The Reimagining Pine Avenue study hopes to address pedestrian and bicyclist safety concerns along heavily-traveled Pine Avenue. – Joe Hendricks | Sun

The city hosted its annual Memorial Day Salute at City Pier Park. The 2020 event was canceled due to the pandemic.

June

Anna Maria Commissioner Joe Muscatello announced he was leaving the commission later that month because he and his wife were moving back to West Virginia to operate a bed and breakfast.

The Manatee County Commission approved the city’s $500,000 funding request to help create a Mote Educational Outreach Center.

Anna Maria: The Year in Review
The city installed a new playground at City Pier Park. – Joe Hendricks | Sun

The city commission agreed to spend $30,909 to install a children’s playground at City Pier Park.

July

The Anna Maria Island Privateer’s Fourth of July parade scheduled for Sunday, July 4, was moved to Saturday, July 3, at the request of CrossPointe Fellowship church officials.

The Anna Maria Island community lost a beloved local figure when Bob “Coop” Cooper passed away on July 3.

Former commissioner Doug Copeland was appointed to serve the remaining months of Muscatello’s commission term.

Mayor Murphy enacted a precautionary local state of emergency as Tropical Storm Elsa approached Anna Maria Island. The tropical storm had little impact on the Island but disrupted the collection of trash that accumulated over the July 4 weekend, which prompted a meeting between the mayor and Waste Management officials.

Duncan Real Estate owner Darcie Duncan celebrated her company’s 20th anniversary.

Assisted by spokesperson Patrick Coyne, Anna Maria homeowners Wendy and Robert Jordan launched the Preserve AMI campaign in opposition to a Florida Department of Environmental permitting decision that could potentially result in a new home being built seaward of the Jordan’s beachfront home at the end of Elm Avenue.

Anna Maria: The Year in Review
The owners of the beachfront home hope to preserve their view and prevent the construction of a new home in front of it.

The mayor expressed his appreciation for the assistance that Manatee County Commissioner Kevin Van Ostenbridge and County Administrator Scott Hopes provided regarding the removal of dead fish and marine life that washed ashore as a result of red tide.

August

Holmes Beach resident Sandy Olson was hired as the assistant manager of the Code Enforcement department.

The Florida Department of Health and the city of Anna Maria hosted a free COVID-19 vaccination clinic at City Pier Park.

Bortell’s Lounge reopened after a three-year renovation project that was delayed in part by the pandemic.

Sea-level rise expert John Englander recommended the city create a “30-year Rising Seas Master Plan” as part of the efforts to prepare for the sea-level rise and higher tides anticipated in the coming decades.

Beach Bums, Robinhood Rentals and Lazy Turtle Beach Rentals agreed to place stickers in their rented golf carts. The stickers remind drivers and passengers of some state laws that apply to operating golf carts on public streets.

September

The city and Mote Marine Laboratory entered into a lease agreement for the Mote Educational Outreach Center. Mote Marine representative Kevin Cooper said he expected the interior buildout and installation to be finished in March, with the facility to open soon thereafter.

October

The city’s weekly farmers market resumed its seasonal operations and will continue each Tuesday through mid-May.

The Anna Maria Chamber of Commerce’s expanded two-day Bayfest celebration returned after being canceled in 2020.

November

Running unopposed, incumbent city commissioners Carol Carter and Jon Crane won additional two-year terms in office. The commission then appointed Robert Kingan to serve a full-two year term to fill the seat vacated by Muscatello and Copeland.

The city’s Old Soldiers & Sailors Veterans Day parade and recognition ceremony returned after being canceled in 2020.

Two Scoops ice cream celebrated its 15-year anniversary.

The second annual Thanks-Living community gathering took place at City Pier Park after being canceled in 2020.

Anna Maria: The Year in Review
Thanks-Living returned to City Pier Park in November.

Former longtime Anna Maria resident and tour boat operator George Glaser passed away at his Bradenton home at the age of 78.

Anna Maria resident Jana Samuels was seriously injured when the golf cart she was driving was struck by a car that crossed into her travel lane in Holmes Beach.

December

Deputy Clerk and Code Enforcement Manager Debbie Haynes retired after six years with the city.

The mayor and commission agreed to share $3,736 of about $850,000 in federal American Rescue Plan (ARP) funds the city will receive over the next two years. The AMI Historical Society, The Island Players and the Anna Maria Island Garden Club are the recipients of those shared funds. The remaining ARP funds will help fund stormwater, drainage and road improvements, and will also help fund the Reimagining Pine Avenue improvements.

Operating with a new name, Santa Stops Here, the city’s annual holiday event, returned to City Pier Park after being canceled in 2020. That evening, The Holiday of Treasures Open House holiday event took place at many participating businesses along Pine Avenue. The city also hosted its third annual Bright Holiday Lights decorating contest.

Funding finalized for Mote Marine facility on City Pier

Funding finalized for Mote Marine facility on City Pier

ANNA MARIA – The Manatee County Commission has officially authorized an interlocal agreement that provides the city of Anna Maria with $500,000 for the buildout and installation of the Mote Educational Outreach Center on the City Pier.

The county commission authorized the interlocal agreement on Tuesday, Oct. 12, after the Anna Maria City Commission approved the Mote Marine lease agreement by a 4-1 vote on Sept. 30.

The $500,000 in county funds is expected to cover the majority of the costs associated with the interior buildout of the city-owned building and the installation of the Mote Marine exhibits. Mote Marine will be responsible for any buildout and installation costs that exceed the $500,000 being provided by the county – with the exception of any additional costs associated with design elements or facility features sought by the city commission beyond those proposed by Mote Marine. The city will reimburse Mote Marine for the buildout and installation costs incurred and then be reimbursed by the county.

The lease agreement reached with Mote Marine in September will not generate monthly or annual rent revenues for the city, and the city will be responsible for the utilities and maintenance costs associated with the educational outreach center that will be staffed and operated at Mote Marine’s expense.

On Thursday, Oct. 14, Anna Maria Mayor Dan Murphy told city commissioners the next step in the process will be the presentation of Mote Marine’s buildout and installation plans. Murphy said those plans will require city commission approval. He also said those plans will be reviewed by the city’s building official and the city’s engineering firm before being presented to the city commission for acceptance or denial.

“If the plans are denied, the deal is off with Mote,” Murphy told the commission. “I chartered our building official and our city engineer with making sure that we’re getting a high-quality product.”

Murphy said he and Public Works Manager Dean Jones plan to meet with Mote Marine CEO and President Michael Crosby within the next 10 days or so to discuss the plans in progress.

“They are already actively developing their plans,” Murphy said.

Murphy said he hopes to bring the plan approval process to quick fruition, but as of last week he was unable to provide an estimated date as to when those plans will be presented to the city commission.

After the September meeting, Mote Marine Vice President of Communications and Strategic Initiatives Kevin Cooper said he expects the buildout and installation to be completed by March 2022, with the Mote Marine facility opening soon after that.

Related coverage

 

Anna Maria and Mote Marine reach pier lease agreement