Skip to main content

Tag: Cortez Bridge

Cortez Bridge construction begins

CORTEZ – The Florida Department of Transportation’s (FDOT) Cortez Road Bridge Replacement Project began on Monday, Nov. 16. The 0.9-mile bridge replacement project spans from 123rd Street West in Cortez to Gulf Drive in Bradenton Beach. 

The bridge will be built in two phases. During phase 1, crews will construct the northern half of the new bridge directly adjacent to the existing bridge. Once that phase is complete, traffic will be shifted onto the new structure, which will allow crews to demolish the old bridge and build the southern half of the new bridge. 

Initially, contractors will begin pile-driving operations and force main utility work along the Hunters Point property. 

A vibratory hammer will drive the pilings into the submerged land. – Ernie Vanderwalt | Sun

Construction will take place between 7 a.m. and 6:30 p.m., but occasional nighttime and weekend work will be conducted. Motorists should expect intermittent daytime and nighttime lane closures, periodic shoulder closures and temporary traffic shifts throughout the work zone. 

Motorists, pedestrians and bicyclists must obey posted signage and be watchful for construction vehicles entering and exiting the roadway. 

The Intracoastal Waterway will remain open to boaters, and the current drawbridge opening schedule remains in effect. 

The project completion is expected in summer 2030. For updates and project details, visit the project website.

Former Seafood Shack site approved as longterm staging area for bridge replacement project 

CORTEZ – Despite objections voiced by residents who said they were misled about how a portion of a county-owned property would be used, Manatee County commissioners voted 5-1 in favor of executing a license agreement with the Cortez Bridge contractor, SEMA Construction, to use county-owned land as a construction staging area for four years. 

Commissioner Jason Bearden cast the lone dissenting vote during the Oct. 20 county commission meeting. 

The license agreement with SEMA pertains to use of the former Seafood Shack property that the county purchased in 2024 for $13 million. 

While briefing the county commissioners, Manatee County Utilities Department Chief Engineer Chad Butzow said the terms of the agreement with SEMA take into account a delay the county caused. Butzow said the county’s water main replacement project that involves installing a new water main under the Intracoastal Waterway is well behind schedule. The old water main conflicts with the pilings SEMA must drive for the first stage of the new bridge, which was supposed to begin in June.

In exchange for the use of the county-owned land, SEMA agreed not to seek delay-associated costs from the county or the state. Butzow estimated that figure to be approximately $1.4 million.

PAST AND FUTURE ALLOWANCES

On June 16, the county commission approved a temporary right of entry agreement with SEMA. On July 28, the temporary agreement was extended for an additional 60 days, through Oct. 16.

The temporary authorization allowed SEMA limited use of the property while staff continued working with SEMA to address the business terms and other concerns associated with the proposed long-term license agreement.

According to background information included in the Oct. 20 meeting packet, “Use of the county property provides SEMA with a staging area adjacent to the bridge project and reduces the need for large construction vehicles and equipment to repeatedly back into or out of the constrained FDOT right-of-way, reducing traffic interruptions and improving construction access.”

The background information notes the county entered into a utility work schedule with the Florida Department of Transportation (FDOT) that requires the county to perform certain utility relocation work before the bridge construction can begin.

The new agreement obligates SEMA to construct a docking, storage and fueling area for the county’s Gulf Islands Ferry service, and to demolish and remove an existing house from the county property.

PUBLIC COMMENT

The staging area plan has changed since it was first presented to the county commission in June. At that time, the plan called for Parcel 2 of the county property to be used as overflow parking for the bridge construction workers.

The new agreement covers two areas. Parcel 1, at the south end of the property, will be used for semi-permanent structures, including a crane access trestle. Located along the water and north of the humpback bridge on 127th Street West, Parcel 2 prompted the most debate.

This map document details the proposed staging areas for the Cortez Bridge construction project. – Manatee County | Submitted

During the Oct. 20 meeting, SEMA representative Justin Oakes said Parcel 2 would serve mainly as overflow parking for employees and for material handling and storage. He said crews would also assemble items such as forms and rebar cages there and offload them directly onto barges. He said the area would be fenced, gated and posted to keep the public out.

Residents from the neighborhoods north of the bridge said the county and SEMA broke their earlier assurances. Mark Szilagy and Jim McConnell said planners and SEMA representatives met with residents on July 10. Szilagy and McConnell said they were told Parcel 2 would be used only for overflow parking of light vehicles, and the residents agreed to that. They said they learned only days before the meeting, from documents posted online, that the site map had been relabeled to include “contractor material assembly staging and parking.”

Oakes said the project is expected to require more than 3,000 truckloads during the 1,200-day contract period – an average of three to five truckloads per day. Without the use of Parcel 2, he said the contractor would have relied heavily on the state-owned right-of-way in front of Tide Tables restaurant, which would require daily lane closures on Cortez Road.

Szilagy said more than 300 residents must pass by the Parcel 2 construction area to enter and leave their neighborhoods, which he said offers only one way in and one way out to Cortez Road.

“We’ve lost our trust again,” Szilagy said, urging the county commission to restore the July terms.

Butzow acknowledged he had overlooked a July email from a neighborhood group objecting to any use of land north of the bridge.

Bearden pressed Oakes on when the staging plan changed. Oakes said he did not know the date and that SEMA did not intend to mislead anyone.

“My issue is transparency,” Bearden said.

Bearden said if the change was known months ago, the county should have discussed it with the residents and a compromise might have been possible.

Tide Tables co-owners Karen Bell and Bobby Woodson said using the state-owned right-of-way in front of their restaurant for construction staging would nearly put them out of business by taking away the restaurant’s parking. Woodson said the restaurant employs about 50 people and serves 500 to 1,000 customers a day. The new agreement avoids the use of the Tide Tables’ parking lot for staging activities.

Woodson also warned that more lane closures would back traffic up to 75th Street during the busy spring season. Bell and Woodson endorsed the commission’s approval of the license agreement with SEMA that allows Parcel 2 to be used for construction staging.

Joe Adorno is the president of Cortez Park Homeowners Inc., the entity that owns the Cortez Park mobile home community property and the neighboring Tide Tables’ property. Adorno said the restaurant is a major source of income for the association. He said trucks and construction equipment cannot share the Tide Tables driveway without disrupting the restaurant operations.

Commissioner George Kruse said he did not want to see the bridge project delayed further. He said denying SEMA’s request would push the work onto the restaurant’s parking area and that could lead to lane closures and long traffic backups.

“The best way negotiation works is everyone walks away a little bit unhappy,” Kruse said.

Related coverage: FDOT hosts Cortez Bridge information session

FDOT hosting Cortez Bridge info session

BRADENTON – On Tuesday, Oct. 20, the Florida Department of Transportation (FDOT) will conduct a preconstruction public information session for the Cortez Road Bridge Replacement Project

The information session will be held in an open house format at Kirkwood Church at 6101 Cortez Road W. in Bradenton from 4 to 6 p.m. The FDOT bridge project team will be on hand and available for discussion.

The project includes the construction of a new Cortez Bridge and the roadway approaches from Gulf Drive/SR 789 to 123rd Street West, a distance of about 0.9 mile.

“The preconstruction public information session is being conducted to share information about construction activities and traffic phasing,” according to the FDOT website.

FDOT project manager Juan Carrillo told The Sun the session is being held at this time because construction will be starting soon.

The new fixed-span bridge will have a 65-foot vertical clearance that allows boat traffic to pass underneath.

FDOT previously hosted a design public meeting in January 2023.

CONSTRUCTION OVERVIEW

According to FDOT, the bridge replacement project will occur in two phases to maintain traffic flow throughout the construction process. During Phase 1, crews will construct the northern half of the new bridge alongside the existing bridge. Once the northern half is completed, traffic will be shifted onto the new bridge, allowing Phase 2 to begin. Phase 2 includes the demolition of the existing bridge and construction of the remaining portion of the new bridge. Construction will be performed using barges and temporary trestles during both phases.

TRAFFIC IMPACTS

To accommodate the construction activities, traffic will be shifted slightly south at both bridge approaches during Phase 1. The shift will allow crews to build new roadway approaches and project features north of the existing roadway. Phase 1 also includes utility relocations and construction of the new Hunters Point Way connection.

During Phase 1 of the construction process, work crews will construct the northern half of the new bridge alongside the existing bridge, allowing Phase 2 to begin. Phase 2 is anticipated to begin in mid-2028 and includes the demolition of the existing bridge and construction of the remaining portion of the new bridge. 

The bridge project cost is approximately $123 million. The construction duration is listed at approximately 1,200 days (about 3.2 years).

Those unable to attend the public information session can submit questions through the project webpage, or by calling Carrillo at 941-708-4429.

FISH board discusses Seafood Shack property plans 

CORTEZ – Discussions about the future of Cortez were at the forefront of the July 6 Florida Institute of Saltwater Heritage (FISH) meeting, with non-board members also participating.

Meeting attendee Paul Dreyfoos is vice president of the Cortez Village Historical Society (CVHS). He spoke about a potential collaboration with historical and environmental groups regarding the future use of the former Seafood Shack property.

The property was purchased by Manatee County in 2024 with the stated intent of using it as a public boat launch and marina. Since then, county discussions have centered on making use of the property as a park, and possibly as a Gulf Islands Ferry stop.

The county-owned property is first expected to be used as a staging area for construction of the new Cortez Bridge, which could take up to four years. With the county’s long-term plans for the waterfront property now delayed by the bridge construction project, Dreyfoos recommends getting out in front of the planning process for the long-term use of the property.

“It pushes the planning cycle way down the road,” Dreyfoos said.

He thinks the Cortez community has an opportunity to help define some of the principles and characteristics for the future use of the county property, and he wants the community to make a strong and cohesive statement regarding those future plans.

Dreyfoos recommends forming a brainstorming group to develop guiding principles and a concept document, and then garnering further collaboration with the environmental, historic preservation and tourism communities.

“The way I framed it for the purpose of the discussion is as an eco-park,” he said. “This is not about boat ramp or no boat ramp. This is about reflecting the aesthetics and values of our community.”

Dreyfoos’ initial design principles include the belief that redevelopment should promote estuary health and incorporate environmental elements consistent with Cortez tradition and economy.

Suggested concepts include a canoe launch, boat ramp access for commercial fishers, boat-to-table food service, land- and water-based recreation, and environmental education for boaters.

“I think one of the things that’s good about your proposal here is pushing the ecological overview,” meeting attendee Allen Garner said. “Regardless of whether it ends up a boat ramp or restaurant or whatever, it’s important to emphasize that point – that whatever goes there should be green and environmentally friendly.”

Several board members expressed interest in participating in a brainstorming group.

“They pushed the Seafood Shack plans back because of the bridge, but that could give us some time and work in our favor,” board member David Cadmus said.

“The goal is to first come up with a concept and then eventually submit that to the county,” Dreyfoos said. “This is an intent to make a wish list and come up with design principles and elements that we feel should be in there. We don’t want to let this just happen to us.”

The discussion is expected to continue during the next FISH board meeting Aug. 3.

FESTIVAL THEME DISCUSSION

The 2027 Cortez Commercial Fishing Festival is seven months away, but planning is already in full swing. A key element of the 45th annual festival is selection of a theme.

FISH Treasurer Jane von Hahmann urged the board to select a theme because a theme-based logo has to be designed. Von Hahmann is resigning from the board effective July 31.

FISH board members discussed a possible theme for the 2027 Cortez Commercial Fishing Festival. – Leslie Lake | Sun

The board discussed the possibility of some variation on “Cortez Fishes for You” as the 2027 theme. A final decision is expected to be made at the board’s Aug. 3 meeting.

Proceeds from the annual festival are used to maintain the 98-acre FISH Preserve.

Cortez Watersports owner optimistic about changes taking place

CORTEZ – Cortez Watersports’ owner John Cadmus is optimistic about the future, despite the pending Cortez Bridge construction project and plans to use the former Seafood Shack property as a construction staging area. 

The construction of the new Cortez Bridge is scheduled to begin in early September. 

Located at 4328 127th St. W., Cortez Watersports sits between the Cortez Bridge and the pending construction staging area. 

Cortez Watersports features WaveRunner, pontoon boat and kayak rentals. Cadmus has also expanded his business operations to include the Cortez Bait Shack, which sells fresh and frozen bait, ice, snacks, cold drinks, boat supplies and fishing gear. 

“We got some live shrimp in here,” he said. 

Cortez Watersports sits between the Cortez Bridge and the former Annie’s Bait & Tackle and Seafood Shack property. – Brian M. Leakeas | Submitted

The Seafood Shack property, which also used to include Annie’s Bait & Tackle, was purchased by Manatee County in 2024. Discussions about the future use of the site have included the possibility of a public boat launch and marina, or a park, and/or a Gulf Islands Ferry landing area. The Manatee County Commission recently approved a 60-day right of entry for the bridge contractor, SEMA Construction, to begin staging bridge construction equipment on the south side of the former Seafood Shack property. SEMA still seeks a long-term right of entry agreement that would allow at least three sections of the county-owned property to be used as a bridge construction staging area for three years or longer. 

CADMUS OPTIMISTIC 

“This area at the Seafood Shack has been stagnant for 40 years,” Cadmus said. “There’s a fine line between ‘old Florida’ and not taking care of things, and that’s what happened over there. It didn’t get taken care of.” 

The Cadmus family has owned the Cortez Watersports property since 1952.

“I have no intention of going anywhere. I’m thoroughly excited about what it’s going to be like,” Cadmus said. “The bridge is going to be beautiful.”

The Cortez Watersports docks are near the Cortez Bridge. – Leslie Lake | Sun

Regarding the demolition of the Seafood Shack building and the boat docks, Cadmus said, “The sea life that they have over there now that all those docks are gone is unbelievable. The dolphins and the manatees all swim around the seawall. They herd the baitfish up around it. They (the county) should be commended for purchasing the property. I’m glad they did because it would be condos.” 

Cadmus acknowledged that his business has been negatively affected by bridge-related preliminary construction work already taking place, but he takes a philosophical approach: “You have to break an egg to make a cake, so we have to deal with it. Hopefully, by allowing them to use the Seafood Shack property, it will make this bridge project go more efficiently. That will be beneficial to businesses here locally.”

Old photos of Cortez line the walls of Cortez Watersports. 

As a nod to old Cortez, a picture of the area that encompassed Cortez Watersports and the former Seafood Shack restaurant hangs on the wall. – Leslie Lake | Sun
Photos of past Cortez fishermen and John Cadmus’ grandmother hang on the wall inside Cortez Watersports. – Leslie Lake | Sun

“We try to honor some of the history of old Cortez,” Cadmus said. “If you look around here in Cortez, a lot of people in this village have been here for a long time, because they persevere. My grandfather, Milton Cadmus, always said, ‘You can’t lean on a shovel and pray for a hole.’”

Learn more at the Cortez Watersports website.

Related coverage: Seafood Shack property to be used as Cortez Bridge construction staging area

Cortez Bridge construction expected to begin in September 

CORTEZ – The long-awaited construction of the new Cortez Bridge is anticipated to start near the beginning of September, according to Florida Department of Transportation (FDOT) spokesperson Ethan Purvis. 

“The current work activities near the bridge are related to Manatee County Utilities’ underground water main crossing, which is to be completed prior to bridge construction,” Purvis wrote in a June 10 email to The Sun. 

In that Manatee County project, sewer and water pipes are being moved to the south side of the bridge. 

Manatee County has been relocating utilities in preparation for the construction of the new bridge. – Leslie Lake | Sun

Purvis stated some of the elements for the new bridge – the precast concrete piles for the foundations and, later, the precast concrete beams – are being constructed offsite. 

Construction of the 0.9-mile-long bridge will take place north of the current bridge. During construction, which is expected to take more than three years to complete, the current bridge will remain open to vehicles. 

The current two-lane drawbridge was built in 1956 and links the mainland on SR 684/Cortez Road to Bradenton Beach. 

In 2023, FDOT shared this conceptual rendering of the new Cortez Bridge. – FDOT | Submitted

The new fixed-span bridge will be 65 feet high and allow larger boats to pass underneath it without the traffic disruptions caused when the current drawbridge is raised so a boat, or boats, can pass through. 

According to the public information presentation FDOT provided in 2023, the new Cortez Bridge will have two 12-foot-wide travel lanes, two 10-foot-wide shoulders and two 10-foot-wide sidewalks – with concrete barricades between the sidewalks and the shoulders.

According to the public information presentation FDOT provided in 2023, the new Cortez Bridge will have two 12-foot-wide travel lanes, two 10-foot-wide shoulders and two 10-foot-wide sidewalks. – FDOT | Submitted
This 2023 rendering shows the anticipated configuration of the new bridge’s vehicular travel lanes, the shoulders and the sidewalks. – FDOT | Submitted

Construction costs are estimated to be more than $130 million. The design cost alone for the bridge was $5.89 million, according to Purvis. 

On Thursday, June 11, Bradenton Beach Mayor John Chappie said he had just been informed of the anticipated September bridge construction start date. 

“I think the bridge will make a tremendous difference in traffic flow – more so for people coming off the Island,” Chappie said. “There are still challenges to get to the bridge, but I believe it will make a big difference.” 

When raised, the current drawbridge brings Cortez Road traffic to a halt. – Joe Hendricks | Sun

Chappie noted the residential development already occurring and the planned future development – both in the general vicinity of the bridge and countywide – will increase the use of the bridge.

“All of the new development that’s happening throughout Manatee County – and in particular, at the corner of 75th and Cortez Road – a lot of those people are going to want to come to the Island,” Chappie said. “So, you take with one hand and give with the other. I think it’s going to be a lot safer for travelers. Safety-wise, it’s going to be a tremendous improvement.”

Utilities work, intersection closure continues near Cortez Bridge

Utilities work, intersection closure continues near Cortez Bridge

CORTEZ – Motorists and others traveling along Cortez Road West, near the Cortez Bridge and the former Seafood Shack property, during Memorial Day weekend will encounter a closed intersection at 127th Street West. The intersection closure is associated with the Cortez Bridge Utility Relocation project.

The Cortez Road/119th Street West intersection remains open but there’s no outlet near the former Seafood Shack property for motorists who turn north on 119th Street West and travel along Harbour Landings Drive and 126th Street West.

Utilities work, intersection closure continues near Cortez Bridge
A “No Outlet” sign remains in place at the intersection of Cortez Road West and 119th Street West. – Joe Hendricks | Sun

126th Street West remains open but motorists can’t make a left turn onto 127th Street West, near the humpback bridge, to reach the nearby Cortez Road intersection.

Utilities work, intersection closure continues near Cortez Bridge
127th Street West is also closed at the 126th Street West intersection, at the humpback bridge. – Joe Hendricks | Sun

According to the project update Manatee County issued on May 15, “Pipe installation and related activities are ongoing in preparation for FDOT’s construction of the new Cortez Bridge, scheduled to begin in 2026. Construction is currently underway east of the Cortez Bridge on the north side Cortez Road West along the northern shoulder of 124th Court West; on 127th Street West between Cortez Road West and 126th Street West; and on the south side of Cortez Road West between 124th Street West and Avenue A. Work in these areas is expected to continue through summer 2025.

Utilities work, intersection closure continues near Cortez Bridge
This map is included in the county’s May 15 project update. – Manatee County | Submitted

“Construction will also be active west of the Cortez Bridge, on the north and south sides of Cortez Road West, throughout the duration of the project, which is expected to be complete in spring 2026. Construction is active Monday through Friday between the hours of 7 a.m. and 7 p.m., with after-hours and weekend work to occur on an as-needed basis. Motorists, bicyclists and pedestrians are asked to remain mindful of construction vehicles, equipment, crews, materials and traffic patterns when traveling in and near the construction areas,” the update says.

Utilities work, intersection closure continues near Cortez Bridge
This project schedule information is included in the May 15 update. – Manatee County | Submitted

The Cortez Road West/127th Street West intersection is closed. - Joe Hendricks | Sun

The Cortez Road West/127th Street West intersection is closed. - Joe Hendricks | Sun

Utilities work is taking place on 127th Street West, near the old Annie’s Bait and Tackle location. - Joe Hendricks | Sun

Utilities work is taking place on 127th Street West, near the old Annie’s Bait and Tackle location. - Joe Hendricks | Sun

Detours, road closures continue

Detours, road closures continue

CORTEZ – The Cortez Bridge utility relocation project will necessitate detours and closures to both vehicle and pedestrian traffic, according to an update from Manatee County officials.

East of the Cortez Bridge, a water main will continue to be installed on the north side of Cortez Road between the area of 127th Street West and 124th Court West. To accommodate this activity, the north shoulder of 124th Court West will remain closed through summer.

Beginning in late April and continuing through early summer, 127th Street West will be closed to vehicle, pedestrian and bicycle traffic at Cortez Road West north to 126th Street West as the contractor installs the pipe. The closure and detour will remain in effect 24/7 until work in this area is complete.

Regular construction activities will take place Monday through Friday between 7 a.m. and 7 p.m. Motorists, bicyclists and pedestrians are asked to remain mindful of construction crews, equipment, materials and traffic patterns when traveling in and near the construction areas. Construction schedules and activities are subject to change due to weather.

The sidewalk and bike lane on the south side of Cortez Road West east of the Cortez Bridge will remain closed between 119th Street West and Avenue B with a detour in place to direct pedestrians and bicyclists. 124th Street West, 124th Street Court West, 125th Court West, Central Avenue, and Avenue A will be closed at Cortez Road West with detours in place to direct motorists.

During active construction, travelers may also experience temporary/intermittent lane closures and flagging operations on the eastbound and westbound lanes of Cortez Road West to allow for the moving and delivery of construction materials and equipment. The sidewalk and eastbound merge lane on the south side of Cortez Road West west of the Cortez Bridge will be closed with detour signs in place.

Cortez bridgetender booth on preservation list

Cortez bridgetender booth on preservation list

CORTEZ – When the new 65-foot-high Cortez Bridge is constructed, it won’t be a drawbridge, so a bridgetender will no longer be needed, and a Cortez group wants to save the bridgetender’s booth at the top of the bridge.

The Cortez Village Historical Society (CVHS) has opened discussions with the Florida Department of Transportation (FDOT) about obtaining and preserving parts of the structure.

“I don’t have a specific idea in mind of what this is going to be,” CVHS President Cindy Rodgers said. “I’m hoping that we can brainstorm some ideas.”

On Aug. 16, representatives from FDOT, including Cortez Bridge Project Manager Ryan Weeks, visited the Cortez Cultural Center.

“This is my first time here and I really would like for us to look at some of the alternative items and walk the bridge, talk about some different things, things that would be easy to remove and display here,” Weeks said.

Rather than transport the entire building, which is a costly endeavor, discussions centered around preserving parts of the building.

“We’re interested in the stuff that’s in there,” Florida Institute for Saltwater Heritage (FISH) member Alan Garner said.

Some of the potential items for preservation discussed by CVHS and FISH members are the controls, lights and swing arms.

“Our discussions at FISH were what does that have to do with the actual village?” FISH Treasurer Jane von Hahmann said. “The more we thought about it, we thought Florida Maritime Museum might be a better fit, but we continue to discuss it.”

“As the link between Cortez and the Gulf Islands, the Cortez Bridge is part of our history. How many times have we traversed that bridge, getting that first glimpse of the sparkling Gulf on the other side, watching the pelicans dive for their dinner and people fishing for theirs,” Rodgers said. “It’s a part of Cortez history and we’d like to preserve what we can of that story for future generations. On the new bridge, there will be no bridgetender building or bridgetender. Eventually, drawbridges will probably become a thing of the past.”

Following tours of the center and the FISH Preserve, representatives from FDOT, CVHS, FISH and the Florida Maritime Museum headed to the bridge for a tour of the bridgetender house.

“I think we had a very good (and full) day – meeting at the Center, Alan and Jane gave a narrated tour of the preserve, lunch at Star Fish, then a trek to the bridge,” Rodgers wrote in an Aug. 16 email to The Sun. “We were able to go inside and to the downstairs area as well, and talk to the bridgetender. Which made me realize we really need to do oral histories with these guys; one of them has done this job for about 30 years – what stories he must have!”

Rodgers said CVHS will compile a wish list of what they would like to have and FDOT will let them know what is possible.

The drawbridge was constructed in 1956 with an estimated 50-year service life and multiple bridge repair and maintenance projects have occurred within the past 20 years.

The design phase of the new bridge began in October 2019 and is anticipated to be completed in spring 2025. The construction project will be awarded to the chosen contractor in summer 2025 with construction slated to begin in late 2025 or early 2026, according to the Cortez Bridge Project website, www.cortezbridge.com.

Multiple departments respond to Cortez Bridge incident

Multiple departments respond to Cortez Bridge incident

BRADENTON BEACH – Bradenton Beach Police officers Devon Straight and Tom Ferrara were at the Circle K near Bridge Street in Bradenton Beach when a concerned citizen came in and told them there was a man on the Bradenton Beach side of the Cortez Bridge screaming for help and running into traffic. The incident began around 7:35 p.m. on May 7.

“Myself and Officer Ferrara quickly responded and soon located the male standing in the middle of Cortez Road next to the Bradenton Beach Police station,” Straight said in a written report. “The male, later identified as Gregory Cawley, appeared wide-eyed and very anxious.”

Officers said that throughout the encounter, Cawley continued to reference people on the scene that weren’t there, including a group of people across the street that were watching the incident. No such group was present on the scene, leading officers to believe he was hallucinating and, due to his dilated pupils, they believed the incident was drug-related.

Straight’s report said Cawley was still fighting police and trying to break free even after EMS arrived and he was handcuffed to a stretcher. Once in the ambulance, he admitted to snorting and consuming crystal meth, although no drugs were found on him. Cawley was taken to HCA Blake Medical Center.

Cortez Bridge meeting features updated replacement plans

Cortez Bridge meeting highlights updated replacement plans

BRADENTON – The Florida Department of Transportation (FDOT) hosted a public information meeting to provide new details about the pending Cortez Bridge replacement project.

The informal setting at Kirkwood Church in Bradenton on Jan. 31 provided attendees an opportunity to view informational panels detailing various design and aesthetic aspects of the fixed-span bridge planned to replace the existing Cortez Road drawbridge, built in 1956.

FDOT representatives were on hand to answer questions and discuss the plans that include several recommendations provided by the Bridge Aesthetics Committee (BAC), which consists of 11 local residents, condominium owners and business owners who have met several times since the committee was formed in mid-2020. Comment sheets allowed attendees to share their written comments on the plans.

The informational slides, a 19-minute video presentation and more can be viewed at the project website. Comments can still be submitted online at the project website. Comments received by Feb. 10 will be included in the meeting summary to be released in late February or early March.

“I hope they got an under- standing of where we’re at with the current design of the bridge and hopefully we’ve been able to answer some of their questions,” FDOT Design Project Manager Ryan Weeks said during the meeting.

FDOT Communications Specialist Adam Rose said, “We’re showing the design of the bridge, as well as taking comments to better fit the bridge needs for the local public and the traveling public. We’re trying to facilitate every aspect of transportation we can on this bridge.”

Rose said FDOT has not yet decided what will happen to the existing drawbridge once the new bridge is completed. He said bridge replacement projects often result in the demolition of the old bridge, but some old bridges are converted into fishing piers instead.

“The department will eventually make that decision. We haven’t made that decision yet,” Rose said.

BAC member Connie Morrow attended the meeting and said, “The Department of Transportation worked with the aesthetics committee from the very beginning. One of the things we asked for was assurance that what we did and what we produced would carry through regardless of the height of the bridge so our efforts would not be a waste.”

Cortez Bridge meeting features updated replacement plans
The new bridge will feature four curved observation points. – FDOT | Submitted

Morrow said the images and information presented Tuesday night accurately reflect the BAC members’ recommendations, which include multi-column bridge piers, a sand-colored bridge and bridge columns, blue railings and light poles, four curved and bench-less observation points and a multi-wave design pattern for the retention walls at both ends of the new bridge.

Project details

The bridge replacement project contract is scheduled to be awarded to a contractor in the summer of 2025 and construction is expected to begin in late 2025 or early 2026.

The new bridge will be built north of the existing bridge, with horizontal curves at each end of the bridge that bring the traffic flow into alignment with the existing roadway. Motorists, pedestrians and bicyclists will continue using the existing bridge until the new bridge is completed.

At its highest point, the fixed-span bridge will provide at least 65 feet of vertical clearance
for vessels passing below. The new bridge will be 68 feet and 3 inches wide and consist of two 12-foot-wide travel lanes (one in each direction), two 10-foot-wide shoulders and two 10-foot-wide sidewalks buffered by concrete barriers.

The roadways approaching the bridge will feature two 11-foot-wide travel lanes (one in each direction), 6-foot-wide bike lanes and 10-foot-wide sidewalks.

The east end of the project will include the construction of a new road called Hunters Point Way that will connect Cortez Road and 127th Street West and provide access to businesses and homes in that area.

Coastal Watersports owner John Cadmus attended Tuesday’s meeting to learn more about the new bridge’s potential impact on his business. He wondered if parking spaces, bike racks and pedestrian amenities would be installed under the Cortez side of the bridge.

“They don’t seem to have parking under the bridge,” he said after speaking to FDOT representatives.

Cortez Bridge meeting features updated replacement plans
Bridge Aesthetics Committee member Connie Morrow shared her insight on the bridge plans, with FDOT Design Project Manager Ryan Weeks standing by her side. – Joe Hendricks | Sun

Coastal Watersports owner John Cadmus discussed the bridge plans with FDOT Design Project Manager Ryan Weeks (right). Joe Hendricks | Sun

“I think it’s going to be a great project. I’m supportive of the bridge, but I’m concerned that there’s no end date for the construction. They couldn’t tell me if it would be two years or five years,” Cadmus said.

Stormwater retention

The plans include three stormwater retention ponds identified as stormwater maintenance facilities along the southwest end of the bridge in Bradenton Beach. One retention area, SMF 3-1, is located near the Bradenton Beach police station. Two more are to be located near the Bradenton Beach Marina, including one, SMF 3-3, that will extend under the new bridge and impact the existing pedestrian and bike pathway there.

Cortez Bridge meeting features updated replacement plans

Bradenton Beach Mayor John Chappie is concerned about the retention area SMF 3-1 being located at the north end of the police department parking lot, which has metal railings that can be removed to provide direct vehicular access from Highland Avenue to Cortez Road if Gulf Drive is blocked during a storm, hurricane or other emergencies.

Cortez Bridge meeting features updated replacement plans
One of the proposed retention ponds would block emergency access to Cortez Road through the removable rails at the end of the police department parking lot. – Joe Hendricks | Sun

“This is vital for public safety,” Chappie said of the railings.

During Tuesday’s meeting, Chappie shared his concerns with Weeks.

“We’ve been told they’ll be making accommodations in that area and they understood our concern, but on the drawing, nothing’s changed. The retention pond is in the way,” Chappie said.

The online video notes the bridge replacement plans don’t include improvements to the Gulf Drive/Cortez Road intersection. Chappie said FDOT is planning a separate complete streets project during the 2023-24 fiscal year that may address safety concerns with the existing sidewalks and crosswalks there.

Related coverage

 

Cortez Bridge presentation details fixed-span bridge

Cortez Bridge presentation details fixed-span bridge

Cortez Bridge presentation details fixed-span bridge

CORTEZ – The Florida Department of Transportation (FDOT) is holding a public information meeting on the Cortez Bridge replacement project on Tuesday, Jan. 31 from 6-8 p.m. in the Kirkwood Presbyterian Church’s Pfrangle Hall at 6101 Cortez Road in Bradenton.

Documents to be presented are available online for those who cannot attend at the project website.

The in-person meeting will be an open house-style event that allows attendees to review the bridge replacement project materials at their own pace. No formal presentation will be given, but meeting attendees can pose questions to project team members and leave written comments as well.

Comments can also be emailed to FDOT Project Manager Ryan Weeks at Ryan.Weeks@dot.state.fl.us, mailed to Ryan Weeks/Florida Department of Transportation, District One, P.O. Box 1249, Bartow, Florida 33831-1249 or submitted online at the project website.

The project materials pertain to the construction of a fixed-span bridge that will replace the existing drawbridge. The materials presented for public review include a 19-minute video, presentation slides, display boards and a 3D animation.

The video provides details about the bridge construction process and the aesthetic design elements selected by the 11-member Bridge Aesthetics Committee (BAC), which includes local residents, business owners and Bradenton Beach Mayor John Chappie.

Cortez Bridge presentation details fixed-span bridge
The Cortez Bridge drawbridge was built in 1956 with an anticipated 50-year service life. – Joe Hendricks | Sun

The narrated video notes the existing drawbridge that will be replaced was constructed in 1956 with an estimated 50-year service life, and multiple bridge repair and maintenance projects have occurred within the past 20 years.

The 90% completed plans will be submitted in the summer of 2023. Final design plans will be submitted in the spring of 2025. The construction project will be awarded to the chosen contractor in the summer of 2025 and construction is slated to begin in late 2025 or early 2026.

The new fixed-span bridge will be 2,930 feet long and consist of 19 spans. The existing drawbridge is 2.616 feet long, with 53 spans.

Cortez Bridge presentation details fixed-span bridge
The new Cortez Bridge will be built north of the existing drawbridge. The top image shows the Bradenton Beach end of the bridge. The bottom image shows the Cortez end of the bridge. – FDOT | Submitted

The new bridge will be built north of the existing bridge, with horizontal curves introduced at each end of the bridge to bring the alignment back to match the existing roadway alignment. Motorists, pedestrians and bicyclists will continue to use the existing bridge until the new bridge is capable of handling that traffic.

A minimum vertical clearance of 65 feet will be provided above the 100-foot-wide navigational channel located below the center of the bridge and delineated by a fender system.

Cortez Bridge presentation details fixed-span bridge
The new bridge will provide at least 65 feet of vertical clearance at its highest point, with a delineated navigation channel below. – FDOT | Submitted

There will be retaining walls at four locations: two at the west end of the bridge and two at the east end of the bridge. The walls will serve as transitions from the bridge to the roadway. The BAC selected a multi-wave design pattern for the walls.

Cortez Bridge presentation details fixed-span bridge
Retaining walls will be built at both ends of the new bridge. – FDOT | Submitted

BAC members considered nine different pier styles and selected multi-column piers with cheek walls. The committee considered nine pedestrian railing alternatives and chose the wave infill pattern. They considered three overlook options and selected the rounded, open overlook shape, without benches.

The BAC members selected the color pallet that will include blue railings, sand/tan for the bridge and piers and white and off-white for accents. They also selected the outside face lighting option.

Cortez Bridge presentation details fixed-span bridge
The new bridge will feature blue railings and light poles. – FDOT | Submitted

Three stormwater retention ponds will be located along the west end of the bridge in Bradenton Beach: one in front of the Bradenton Beach police station, one in front of the Bradenton Beach Marina and another in front of the Bradenton Beach Marina that will extend under the first span of the bridge and require the existing pedestrian and bike path under the bridge to be reconfigured.

Cortez Bridge presentation details fixed-span bridge
A new road called Hunters Point Way will connect Cortez Road to 127th Street West. – FDOT | Submitted

One retention pond will be located on the east end of the bridge, near the Hunters Point Resort & Marina property. The eastern side of the project will also include the construction of a new road called Hunters Point Way that will connect Cortez Road and 127th Street West and provide access to the Seafood Shack, Tide Tables and the other businesses and homes in that vicinity.

Cortez Bridge meeting scheduled

Cortez Bridge meeting scheduled

CORTEZ – The Florida Department of Transportation (FDOT) will host a public information meeting for the pending Cortez Road bridge replacement project.

FDOT’s in-person presentation is scheduled on Tuesday, Jan. 31 from 6-8 p.m. in the Kirkwood Presbyterian Church’s Pfrangle Hall at 6101 Cortez Road in Bradenton.

The in-person meeting will be an open house-style event that allows attendees to review the bridge project materials at their own pace. Attendees can pose questions and comments to attending project team members but no formal presentation will be given.

FDOT will provide online access to the public meeting materials that address design details and aesthetics, construction phasing and traffic maintenance associated with its plans to replace the existing drawbridge, built in 1956, with a fixed-span bridge that at its highest point will provide 65 feet of vertical clearance for vessels passing below it. The informational meeting is not advertised as a continuation of the fixed-span vs. drawbridge debate that continues to be a source of opposition for some residents and elected officials.

Cortez Bridge meeting scheduled
The existing Cortez Bridge drawbridge was built in 1956. – Joe Hendricks | Sun

“The same information will be presented at both the live in-person venue and online at the project website so attending both is not needed,” according to the recent meeting-related newsletter distributed by FDOT.

On Tuesday. Jan. 24, the online meeting materials will be posted at the FDOT District One road projects website.

Comments or questions may be submitted during the public meeting, at the project website or to FDOT Project Manager Ryan Weeks by phone at 863-519-2837, by email at Ryan.Weeks@dot.state.fl.us, or by regular mail addressed to Ryan Weeks, Florida Department of Transportation, P.O. Box 1249, Bartow, Florida 33831.

“While comments about the project are accepted at any time, please submit your comments by Feb. 10 to be included in the meeting summary,” the FDOT newsletter says.

According to the road projects website, “The project includes the bridge and roadway approaches from SR 789/Gulf Drive (in Bradenton Beach) to 123rd Street West (in Cortez), a distance of about 0.9 miles.”

The website notes FDOT previously formed a Bridge Aesthetics Committee (BAC) consisting of community representatives from Cortez and Bradenton Beach to provide input on the bridge’s aesthetics. The committee members include Joe Adorna, Mike Bazzy, Karen Bell, Bradenton Beach Mayor John Chappie, David Galuska, Connie Morrow, Ann Marie Nicholas, Joe Rogers, Jeff Vey, Gloria Weir and Bobby Woodsen.

Several BAC meetings and additional small group meetings occurred between August 2020 and November 2021 and future meetings will be added as more information becomes available.

Cortez Bridge meeting scheduled

The fixed-span bridge will include a buffered pathway for pedestrians and bicyclists. – FDOT | SubmittedAccording to the website, “To date, the BAC has determined the following, may be altered in the final design:

  • “Preference is for aesthetically enhanced multi-column pier with a waterline footing. The exterior face of the column would be in line with the exterior face of the bridge deck. Cheekwalls would extend from the top of the pier to the underside of the deck at all pier locations.
  • “Preference is for four overlooks, located on the north and south side of the bridge at the two piers on either side of the main channel.
  • “Preference for substructure lighting on the exterior faces of the pier columns.
  • “A custom ‘wave’ infill pattern is suggested for the bridge pedestrian railings.”

FDOT’s roads projects website also includes a link to a project-specific website.

According to the Cortez Bridge website, “The design phase of Cortez Bridge began in October 2019 and is anticipated to be completed in spring 2025. Right-of-way is funded in fiscal years 2022, 2023 and 2024. Construction is funded in fiscal year 2025.”

According to the project-specific website, “The need for the project was based on the functional obsolescence and structural condition of the existing bridge. Due to the naturally corrosive saltwater environment, the bridge continues to deteriorate and will need additional repairs in the future. The condition of the bridge is anticipated to deteriorate further as the structure has exceeded its 50-year service life. Replacement of the bridge will address the condition of the structure and reinforce the connection between Anna Maria Island and the mainland of Manatee County.”

Judge rules in favor of FDOT in Cortez Bridge challenge

Judge rules in favor of FDOT in Cortez Bridge challenge

CORTEZ – U.S. Magistrate Judge Anthony Porcelli has ruled against the four plaintiffs opposing the Florida Department of Transportation’s (FDOT) plans to construct a fixed-span bridge between Cortez and Bradenton Beach, granting FDOT’s motion for summary judgment.

With construction slated to begin as early as 2026 according to FDOT officials, the fixed-span bridge will provide 65 feet of vertical clearance for vessels passing under it.

The new bridge will replace the aging drawbridge that currently provides 17 feet of vertical clearance when the bridge is down.

As noted in Porcelli’s order, “The existing Cortez Bridge was constructed in 1956 to replace the original 1921 wooden bridge connecting Anna Maria Island with the mainland in Manatee County. As constructed, the existing Cortez Bridge consists of an undivided, two-lane, low-level bascule (drawbridge) structure. The results from several bridge inspection reports conducted since 2008 show that the Cortez Bridge has become functionally obsolete and structurally deficient.”

Judge rules in favor of FDOT in Cortez Bridge challenge
Built in 1956, the Cortez Bridge drawbridge is slated to be replaced with a higher fixed-span bridge. – Joe Hendricks | Sun

In the United States District Court Middle District of Florida’s Tampa Division, Porcelli issued his 57-page written order on Aug. 5. The order pertains to the complaint for declaratory and injunctive relief the plaintiffs filed in 2020.

The plaintiffs in the legal action are former Manatee County Commissioner Joe McClash, former Manatee County Commissioner and Cortez resident Jane von Hahmann and Cortez residents Linda Molto and Joe Kane. The complaint names FDOT and FDOT Secretary Kevin Thibault as defendants.

In part, the plaintiffs sought from the federal court:

  • A declaratory judgment that FDOT, when deciding on a fixed-span bridge, violated the National Environmental Policy Act (NEPA) and the Administrative Procedure Act.
  • An order to vacate the acceptance/approval of FDOT’s Location and Design Concept Acceptance for a 65-foot-high fixed-span bridge that would have significant impacts on the surrounding community.
  • An order to vacate FDOT’s Type 2 categorical exclusion determination.

The plaintiffs also sought a 35-foot drawbridge option as a viable bridge replacement alternative that would not cause the same significant impacts as a 65-foot high, fixed-span bridge.

According to Porcelli’s order, the plaintiffs challenged FDOT’s decision to replace the existing 17-foot-high drawbridge with a 65-foot-high, fixed-span bridge, and FDOT’s decision to forgo an environmental impact statement or an environmental assessment and proceed instead using a categorical exclusion to the National Environmental Policy Act.

The plaintiffs contended FDOT violated the act by arbitrarily and capriciously relying on
an inapplicable categorical exclusion to exempt a major federal action – the construction of the new bridge – from FDOT’s obligation to perform either an environmental impact statement or an environmental assessment. Case law cited in Porcelli’s order

notes the National Environmental Policy Act establishes procedures for agencies to follow when addressing environmental impact issues and procedures.

“NEPA regulations authorize the use of exclusions for those categories of actions which do not individually or cumulatively have a significant effect on the human environment, and which have been found to have no such effect in procedures adopted by a federal agency in implementation of these regulations,” according to Porcelli’s order.

“Plaintiffs contend the Cortez Bridge Replacement Project does not qualify for a categorical exclusion, but FDOT disputes that contention. FDOT contends that the Cortez Bridge replacement project satisfies the criteria for a categorical exclusion,” according to Porcelli’s order.

Plaintiff reactions

When asked about continuing to challenge to fixed-span bridge, McClash said a potential appeal is possible.

Judge rules in favor of FDOT in Cortez Bridge challenge
Joe McClash led the legal challenge to FDOT’s proposed fixed-span bridge. – Joe Hendricks | Sun

When contacted by email, von Hahmann was more animated in her response to Porcelli’s ruling.

“Very sad and very discouraged,” von Hahmann wrote in her response to The Sun. “I feel like there is no road for the general citizenry to take to have their voices and concerns heard at any level of government anymore. I say that because we were involved as citizens from the get-go. In this last go-around, which started in 2013, we continually and consistently voiced our concerns and objections to a high-level fixed-span bridge.

“In fact, during public meetings held regarding this bridge, the vast majority of those who have to live with this atrocity asked that a lower level, less impactful choice be made. All total, there were 1,229 public comments received on the bridge. Of those, 863 citizens (70%) chose the no-build/rehab option or a 35-foot bascule bridge (drawbridge) replacement and 366 citizens (30%) chose a 65-foot, high-fixed bridge. The bottom line is residents of Cortez and Anna Maria Island, especially Bradenton Beach, be damned,” von Hahmann wrote in her response.

In 2021, McClash and von Hahmann asked the Bradenton Beach City Commission to join the legal challenge as co-defendants. The city commission declined that request.

Judge rules in favor of FDOT in Cortez Bridge challenge
In 2021, Cortez resident Jane von Hahmann encouraged the city of Bradenton Beach to join the legal challenge. – Joe Hendricks | Sun

In response to Porcelli’s order, Von Hahmann was asked if she’ll continue challenging the fixed-span bridge.

“No, I am done. I no longer believe we as citizens can challenge the government at any level and win,” she responded.

Mayor hopes to celebrate Bridge Street’s 100th anniversary

Mayor hopes to celebrate Bridge Street’s 100th anniversary

BRADENTON BEACH – Mayor John Chappie wants to recognize the 100th anniversary of Bridge Street with a celebration.

The street was once at the foot of the bridge leading to Anna Maria Island from Cortez before a new bridge was built. The Bradenton Beach pier now stands in the footprint of the original bridge.

Chappie, a member of the city’s Community Redevelopment Agency (CRA), asked the board last month for $10,000 to purchase holiday banners to place on light poles down Bridge Street. He hopes some of the money will be used to purchase banners commemorating the 100-year anniversary of the historic commercial area. CRA members approved the funds and expressed preliminary support for the proposed celebration.

During the CRA meeting on July 6, he provided additional details on his anniversary celebration plans.

Mayor hopes to celebrate Bridge Street’s 100th anniversary
Mayor John Chappie is leading the efforts to recognize and celebrate Bridge Street’s 100th Anniversary. – Joe Hendricks | Sun

“We just are finishing up with our hundredth year of Bridge Street existing,” Chappie said, adding that Bridge Street is believed to be the longest existing commercial area on Anna Maria Island. “100 years is pretty cool.”

Chappie told the board he recently spent a couple of hours doing research at the Anna Maria Island Historical Society Museum and he couldn’t find any specific details as to exactly when the street was renamed Bridge Street, so he’s using the construction of the original Cortez Bridge, which began in 1921, as a start for the 100-year timeline.

“As the bridge was being built, a hurricane came late in 1921 and they had to rebuild what was destroyed in 1922, so we’re still within that 100-year timeframe,” he said.

Mayor hopes to celebrate Bridge Street’s 100th anniversary
In 1956, the original Cortez Bridge on the right was replaced with the new drawbridge being built on the left. – Manatee Public Library Digital Collection | Submitted

Construction of the Cortez Bridge was completed in 1922, according to the book “Anna Maria Island: The Early Days, 1893-1940,” written by late Island historian Carolyne Norwood.

“The bridge from Cortez to Cortez Beach (now known as Bradenton Beach) was completed in 1922. Cortez Beach soon became the commercial center of the Island – just in time for the Florida boom and prohibition! By 1927, Cortez Beach had a population of 75. There was a village store, a gas station, the Bayside Inn (now The Bridgetender Inn), the Bath House and the popular Pagoda Dance Hall. Among the many characters were carpenters, bookkeepers, bootleggers and ladies of the night,” Norwood wrote.

Mayor hopes to celebrate Bridge Street’s 100th anniversary

This photo of the Bath House was taken in 1922 in the city then known as Cortez Beach. – Manatee Public Library Digital Collection | Submitted“The Bath House was on the Gulf beach at the end of Bridge Street. South of the Bath House stood the huge Pagoda Dance Hall. People were charged to dance and be served setups for the rum, homebrew and moonshine they bought from the locals. Weekends and holidays, as many as four hundred Model T’s a day would cross the bridge from four surrounding counties, since Cortez Beach had the only bathhouse and dance hall on the midwest coast of Florida. This was the heyday of Cortez Beach. Al Capone stayed at the Albion Inn (in Cortez) in 1928 amid rumors of his arranging for illegal rum to go to the Midwest from Cuba,” Norwood wrote.

Mayor hopes to celebrate Bridge Street’s 100th anniversary
This photo is included in Carolyne Norwood’s book, “The Early Years, 1893-1940.” – Submitted

In 1956, the original bridge was replaced with the current drawbridge, now slated to be replaced with a higher fixed-span bridge.

Chappie told the CRA members he’s already discussed with some Bridge Street business owners the prospect of hosting an anniversary celebration event in September.

“I’m putting out feelers and I’ll be reporting back,” he said.