Skip to main content

Tag: bid proposals

Second Pine Avenue RFP authorized

Second Pine Avenue RFP authorized

ANNA MARIA – As part of a block-by-block implementation strategy, the city of Anna Maria is issuing a request for proposals (RFP) for phase 1-B of the Reimagining Pine Avenue brick paver sidewalk installation project.

Phase 1-B calls for the installation of new pervious brick paver sidewalks and new crosswalks along Pine Avenue, between North Shore Drive and Crescent Drive.

Second Pine Avenue RFP authorized
The unpaved pedestrian paths along Pine Avenue will be replaced with brick paver sidewalks. – Joe Hendricks | Sun

In each of the four initial construction phases, brick paver sidewalks will be installed along both sides of Pine Avenue where no concrete sidewalks currently exist, including the unpaved pedestrian paths that meander inward toward the business entrances. The existing concrete sidewalks along Pine Avenue will remain in place until they are replaced in a future phase or phases of the project.

The city commission approved the phase 1-B RFP issuance during its June 27 meeting.

Mayor Dan Murphy sought the phase 1-B RFP at this time so construction companies interested in phase 1-A can also submit bids for phase 1-B. He said if the same company is awarded the phase 1-A and 1-B projects, they would only have to mobilize their equipment, materials and labor resources one time, which could produce some cost savings for the city.

City Clerk LeAnne Addy did not specify an exact phase 1-B bid submis­sion deadline but she said those bids are due in approximately 27 days, which is on or around July 25.

On June 13, the commission authorized the issuance of the phase 1-A RFP for new brick paver sidewalks and crosswalks along Pine Avenue between Gulf Drive and North Shore Drive. Phase 1-A bid proposals are due July 17.

The phase 1-C RFP for the section from Crescent Drive to Tarpon Street is expected to be issued on or around July 15 and the RFP for the Tarpon Street to Bay Boulevard section of the project is expected to be issued on or around July 31.

On June 13, Murphy said he expects phase 1-A to be completed by the end of September and all four initial phases to be completed by the end of November.

Second Pine Avenue RFP authorized
Pedestrians don’t always follow the unpaved meandering paths along Pine Avenue and choose to walk along the street instead. – Joe Hendricks | Sun

After the four phase 1 sections are completed, the mayor and commission will turn their attention to replacing the existing concrete sidewalks with new brick paver sidewalks. New streetlights will also be installed along Pine Avenue as part of the safety improvement project that will later extend to Spring and Magnolia avenues.

Another Reimagining Pine Avenue decision looms

Another Reimagining Pine Avenue decision looms

ANNA MARIA – For the fourth time, commissioners will soon be asked to accept or reject a Reimagining Pine Avenue bid proposal submitted by the C-Squared construction company.

On March 25, City Clerk LeAnne Addy opened the only bid received in response to the city’s fourth request for proposals (RFP) since 2022. Despite being previously rejected three times, Sarasota-based C-Squared CGC Inc. again submitted the only bid.

The RFP sought proposals to construct a one-block Reimagin­ing Pine Avenue prototype between Gulf Drive and North Shore Drive. The proposed prototype area would include the same safety improvements desired along the entirety of Pine Avenue – brick paver sidewalks along both sides of the street, new crosswalks and new streetlights.

The sidewalks and crosswalks are to be funded using a $1.28 million state appropriation that the Florida Legislature and Gov. Ron DeSantis approved in 2022. An additional $1.4 million state appropriation was approved in 2023 to expand the project to include similar safety improve­ments along Spring and Magnolia avenues, although no formal plans for those two additional streets have been presented.

Another Reimagining Pine Avenue decision looms
City Clerk LeAnne Addy opened C-Squared’s latest bid on March 25. – Joe Hendricks | Sun

While seated in the commis­sion chambers, Addy opened C-Squared’s sealed bid with only a C-Squared representative and The Sun present. In accordance with previously-established city protocol, only the name of the bidder was made public. No additional details, including the proposed price, were made public. The bid details will be made public when C-Squared’s proposal is presented for city commission discussion and consideration. The agenda for the commission’s April 11 meeting includes a Pine Avenue RFP update but it doesn’t indicate whether any formal commission decision-making is expected.

Another Reimagining Pine Avenue decision looms
City officials are concerned about bicyclists’ safety along Pine Avenue. – Joe Hendricks | Sun

If the commission ulti­mately rejects C-Squared’s latest proposal, the city could issue a fifth RFP, this time seeking bids for all of Pine Avenue or the entire expanded three-street project. In February, Commissioner Mark Short noted the city has until the end of the calendar year to spend the appropriation funds approved in 2022. Although unlikely, the mayor and commission could abandon the project and forego the state funds if a contractor can’t be secured.

C-Squared hasn’t done any previous projects for the city of Anna Maria, but the company has completed city projects in Bradenton Beach and in Holmes Beach. Several years ago, C-Squared replaced the failing brick paver crosswalks on Bridge Street in Bradenton Beach that were installed by another company.

C-Squared completed the city center project for the city of Holmes Beach in 2023. The company is currently named as a co-defendant in a civil lawsuit pertaining to the 2023 death of pedestrian Miriam Trotter, who was struck by a vehicle driven by Michael Ritchie in a C-Squared work zone and traffic manage­ment area associated with the city center project.

The lawsuit alleges C-Squared and Ritchie share re­sponsibility for the fatal accident and alleges C-Squared failed to maintain a safe work zone. According to court documents, Ritchie denies responsibility for the accident and faults C-Squared for not maintaining a safe work zone; and C-Squared denies responsibility for the actions of Ritchie and Trotter.

PAST PROPOSALS

None of the four Reimagining Pine Avenue RFPs produced bid proposals from any firm other than C-Squared.

The initial feasibility study and planning process began in mid-2021 with contracted project engineer Gerry Traverso leading those efforts.

Another Reimagining Pine Avenue decision looms
Along some portions of Pine Avenue, unpaved meandering paths are used by some pedestrians and ignored by others. – Joe Hendricks | Sun

During a series of public meetings, several ideas and concepts were proposed, discussed and in some cases rejected. The rejected ideas included transforming Pine Avenue into a one-way street, with Spring or Magnolia also serving as a one-way street. The commission also rejected installing a roundabout/delivery truck turnaround area at the end of Pine Avenue, near the City Pier.

The commission discussed potentially eliminating approximately 50 parallel parking spaces along Pine Avenue to create space for bike paths and/or multi-use paths. Some past and present commissioners expressed support for doing so, but eliminating those parking spaces has never garnered the majority support of the city commission.

Another Reimagining Pine Avenue decision looms
City officials hope additional and enhanced crosswalks will improve pedestrian safety. – Joe Hendricks | Sun

In February 2022, the commission approved Traverso’s conceptual plans for the sidewalks and crosswalks.

The following month, the commis­sion authorized the issuance of the first Reimagining Pine Avenue RFP for the installation of new sidewalks, crosswalks and streetlights along Pine Avenue. That RFP produced a single C-Squared bid for approximately $2 million, with a significant portion of the proposed costs associated with streetlighting.

In May 2022, the commission voted 4-0 in favor of rejecting C-Squared’s first bid and issuing separate RFPS for the sidewalks and the streetlight­ing, with the city self-installing the crosswalks. In response to a second RFP later issued for the Pine Avenue sidewalks, C-Squared bid $1.09 million to install brick paver sidewalks or $1.22 million to install rubberized Flexi-Pave sidewalks.

In July 2022, the commission authorized Murphy to engage in further fact-finding discussions with C-Squared regarding their second proposal, and that month Gov. Ron DeSantis approved the city’s $1.28 state appropriation request.

In August 2022, Murphy received a letter from the Florida Department of Transportation (FDOT) informing him that FDOT would oversee the expenditure of state funds and the Reimagining Pine Avenue plans and RFPs required FDOT review and approval. That led to the second C-Squared proposal being rejected, even though Murphy said it was a good proposal.

It was later learned that using state funds to install new streetlights would subject the city to FDOT’s less aesthetically pleasing lighting standards. The commission agreed to instead use leftover federal American Rescue Plan funds to pay for the streetlights.

In March 2023, the city issued a third RFP, again for the Pine Avenue sidewalks and again producing a single bid from C-Squared. When Murphy initially reviewed that bid with the commission the following month, he said it was approximately $418,000 higher than the previous bid.

Murphy said the increase could be partially attributed to the RFP requesting crushed granite, rather than crushed concrete, be used as fill material for the drainage trenches below the new sidewalks. Murphy noted labor costs also increased since the previous bid was received.

Later that month, the commis­sion voted 4-1 in favor of rejecting C-Squared’s third proposal. Commis­sioner Jon Crane opposed rejecting the bid because he didn’t feel the city would get a better proposal.

Another Reimagining Pine Avenue decision looms
Many forms of transportation are utilized along Pine Avenue. – Joe Hendricks | Sun

In November, Murphy proposed the one-block Reimagining Pine Avenue prototype. In February, Murphy told the commission Traverso estimated the one-block prototype might cost $425,000 to $450,000. Murphy said the prototype area would serve as a test area that would provide additional insights as to what unexpected challenges and obstacles might be encountered along the rest of Pine Avenue. Murphy acknowledged that he wasn’t sure the smaller-scale prototype project would attract any or many bidders.

In late February, the city issued the fourth RFP that produced the latest bid from C-Squared, which brings the city to its current juncture with the long-delayed project.

Four bids received for City Pier grill and bait shop

Four bids eyeing City Pier grill and bait shop

UPDATED Aug. 22, 2020 – ANNA MARIA – Four local entrepreneurs interested in operating a grill and bait shop on the new City Pier have submitted bid proposals to the city of Anna Maria.

The bid proposals received are in response to the request for proposals (RFP) the city recently issued seeking a tenant to lease the 300-square-foot bait shop building at the T-end of the new pier.

The city seeks a tenant who will operate a takeout grill that offers a limited menu throughout the day in addition to selling bait and possibly offering additional fishing supplies.

Four bids received for City Pier grill and bait shop
The bidders hope to lease the city-owned bait shop building on the Anna Maria City Pier. – Joe Hendricks | Sun

The deadline to submit a proposal was 1 p.m. on Friday. A few minutes after that deadline passed, Mayor Dan Murphy opened the four bid proposals and announced who submitted them.

The four bidders are F.P. Growth Partners; Brian Seymour, Vic Mattay and Nicholas Graham; Sarah Baldwin/Tevatan LLC and Harry’s Continental Kitchens.

Four bids received for City Pier grill and bait shop
Kim Nemeth, Brian Seymour and Patrick Coleman attended Friday’s bid opening, with Public Works Manager Dean Jones also present. – Joe Hendricks | Sun

Patrick Coleman represented F.P. Growth Partners at the public bid opening held at city hall in the city commission chambers. F.P. Growth Partners’ business operations include the Poppo’s Taquerias on Pine Avenue in Anna Maria and on Manatee Avenue in Bradenton.

Seymour is the owner/operator of the Anna Maria General Store and Deli on Pine Avenue that leases space to Mattay and his Dips Ice Cream shop. Graham is the co-owner and operator of Graham Slam fishing charters in Cortez.

Anna Maria resident Kim Nemeth represented Tevatan LLC. Nemeth is the manager of Paradise Boat Tours and Bridge Street Bait Shop at the foot of the Bridge Street Pier in Bradenton Beach.

Tevatan LLC is led by CEO Sarah Baldwin and her father, Sherman Baldwin, who serves as the LLC’s general manager. Tevatan also operates Hart’s Landing in Sarasota in space leased from that city.

Harry’s Continental Kitchens is located in Longboat Key and was not represented at Friday’s bid opening.

Waterfront Restaurant & Craft Bar owner Jason Suzor and Star Fish Co. restaurant owner Karen Bell participated in the recent pre-bid meeting but neither submitted a bid proposal.

Murphy said he will now review the four bid proposals that will also be provided to city commissioners. The proposals will not be made public until placed on an agenda for a future city commission meeting or a special city commission meeting to be held within the next 30 days.

When the bid proposals are presented for commission discussion at a public meeting, each commissioner will individually rank the bidders and their proposals according to their personal preferences. One point will be awarded for a commissioner’s first choice, two points will be awarded for a commissioner’s second choice and so on. The bidder and proposal with the lowest combined score will then be given the opportunity to attempt to negotiate a lease contract with Murphy and the city.

According to the RFP, the city reserves the right to discard any or all bids.

During Friday’s bid opening, Murphy said he hopes to have the grill and bait shop open by the first of the year at the latest, and much sooner than that if all goes well.

Four bids received for City Pier grill and bait shop
While seeking a tenant for the bait shop building to the left, the city currently has no plans for the larger building to the right. – Joe Hendricks | Sun

The city currently has no plans to resume its search for another pier tenant to operate a full-service restaurant in the larger of the two city-owned buildings at the T-end of the new City Pier. At this time, the future use of the larger pier building has not been determined.

Related coverage

 

Grill and bait shop tenant sought for City Pier

 

Commission rejects Ugly Grouper pier lease offer