Cortez Bridge construction begins

On Monday afternoon, a crane mounted on a work barge prepared to drive a test piling along the northeast side of the Cortez Bridge. – Ernie Vanderwalt | Sun

CORTEZ – The Florida Department of Transportation’s (FDOT) Cortez Road Bridge Replacement Project began on Monday, Nov. 16. The 0.9-mile bridge replacement project spans from 123rd Street West in Cortez to Gulf Drive in Bradenton Beach. 

The bridge will be built in two phases. During phase 1, crews will construct the northern half of the new bridge directly adjacent to the existing bridge. Once that phase is complete, traffic will be shifted onto the new structure, which will allow crews to demolish the old bridge and build the southern half of the new bridge. 

Initially, contractors will begin pile-driving operations and force main utility work along the Hunters Point property. 

A vibratory hammer will drive the pilings into the submerged land. – Ernie Vanderwalt | Sun

Construction will take place between 7 a.m. and 6:30 p.m., but occasional nighttime and weekend work will be conducted. Motorists should expect intermittent daytime and nighttime lane closures, periodic shoulder closures and temporary traffic shifts throughout the work zone. 

Motorists, pedestrians and bicyclists must obey posted signage and be watchful for construction vehicles entering and exiting the roadway. 

The Intracoastal Waterway will remain open to boaters, and the current drawbridge opening schedule remains in effect. 

The project completion is expected in summer 2030. For updates and project details, visit the project website.