Piney Point withstands Debby

Piney Point 2024
Piney Point 2024

PALMETTO – Severe weather associated with then-Tropical Storm Debby passed over the Piney Point site on Aug. 4-5, producing high winds and more than 9 inches of rain, according to the Florida Department of Environmental Protection (FDEP), which says the rainfall was well within the plant’s storage capacity of 90 inches.

The Piney Point property is the site of a former phosphate processing plant closed for several years. Wastewater holding ponds were built on the crest of phosphogypsum stacks at the site, less than two miles from Tampa Bay and near two state aquatic preserves.

In April 2021, a breach in the outer wall of one of the retention ponds resulted in approximately 215 million gallons of water containing high levels of nitrogen and phosphate being intentionally discharged into nearby waters to avoid flooding nearby homes and businesses. The discharge worsened a bloom of the toxic algae red tide that lasted six months, causing fish kills and respiratory irritation.

Afterwards, a 3,300-foot-deep well was built near Piney Point at 3105 Buckeye Road to permanently store the wastewater being drained from the stacks, a process still in progress.

In an Aug. 9 FDEP status update, it was reported that:

• The site has received 9.55 inches of rain so far this month, including approximately 9.5 inches from Hurricane Debby. Piney Point has received approximately 44.49 inches of rain since Jan. 1.

• The storage capacity for additional rainfall at the site is over 90 inches. This capacity is expected to change with rainfall amounts and adjusted water management activities at the site.

• Approximately 160.2 million gallons are currently held within the NGS-South compartment. Pond level readings are expected to fluctuate due to a host of factors, including wind/associated waves in the pond, rainfall and water management activities.

“FDEP has been in contact with the court-appointed receiver and confirmed there is no identified damage to the compartment systems and there are no other water management concerns,” according to the Aug. 9 update. “FDEP is working closely with the court-appointed receiver to continue site evaluations and manage water levels. A full site inspection is underway to assess any post-storm impacts.”

In July, FDEP reported that final closure procedures for Piney Point are moving forward.

“Forgen LLC, the project contractor, has completed the liner installation on top of the OGS-South compartment and is now working with court-appointed receiver Herb Donica to complete the final details for closure, including placing soil cover and grass over the area so that it will no longer accumulate rainwater,” according to the July update.

Residents can find the latest information on the status of the site, response activities and water quality at ProtectingFloridaTogether.gov/PineyPointUpdate.