Commission reduces stop-work order penalty

The construction of this Bradenton Beach home was halted by a stop-work order in early October. – Leslie Lake | Sun

BRADENTON BEACH – City commissioners voted unanimously to reduce an after-the-fact building permit penalty for a new home under construction at 1207 Gulf Drive S.

The new home is being built by the Mason Martin Builders construction company owned by Frank Agnelli and Jake Martin. The residential property is owned by Air Head N Bed LLC.

A city-issued stop-work order brought the construction process to a halt on or around Oct. 2. The penalty to be imposed for the work done without a city-issued building permit was discussed during the Nov. 19 city commission meeting.

After a lengthy discussion, the commission approved imposing a $21,477 penalty that doubles, rather than triples, the initial $21,477 permit fee and brings the permit fee to $42,954.

The sample motion included in the Nov. 19 meeting packet asked the commission to approve, approve with changes, deny or adopt a $38,794 reduction in the after-the-fact building permit penalty for Mason Martin Builders. That recommended action would have reduced the penalty for working without a building permit from $48,794 to $10,000. The divided commission did not support reducing the penalty to $10,000.

Building Official Ben Carr recommended a $10,000 penalty for work done without a building permit. – Leslie Lake | Sun

Building Official Ben Carr told the commission that Mason Martin Builders obtained a floodplain permit on May 14, and the construction then began and continued without a building permit. Carr said the floodplain permit did not authorize construction of a new residence, and a building permit was not obtained.

Carr said city inspectors recorded 10 inspections conducted under the floodplain permit from June 16 through Sept. 18, with nine passed inspections and one partially passed inspection.

The permitting discrepancy was noticed on Oct. 2, and a stop-work order was issued that day. Carr said the city’s code enforcement officer found the unpermitted work continuing the following Monday and the work was again ordered to stop.

Mason Martin applied for an after-the-fact building permit Oct. 13. The stop-work order remained in effect as of Nov. 20.

The staff report Carr provided the commission in advance of the Nov. 19 meeting proposed reducing the proposed triple-fee penalty by $38,794 and imposing a $10,000 penalty instead.

The staff report notes the recommended relief was based on the project’s documented inspection history and the maximum fine amount allowed by Florida law.

“The $10,000 recommendation uses an independent reference point. Under Florida Statutes, the state’s contractor licensing board may impose fines up to $10,000 per violation, including permit violations,” the staff report says.

FIRST MOTION FAILS

Commissioner Robert Talham, a former licensed contractor, said he opposed using an independent review of the state statute to determine the penalty amount, but he later supported the $10,000 penalty.

“We have our own laws on this,” Talham said in reference to the city’s land development code.

Carr said the state’s $10,000 maximum fine served as a basis for staff’s recommendation. He said the reduction was justified because the city performed 10 inspections before the permitting issue was raised.

Carr said inspections were conducted by the Tew & Taylor firm that provided the city’s contracted building services before Carr was hired and became a full-time city employee in late September.

Commissioner Scott Bear said the city’s building official at the time (Mike Alexander) made an initial mistake by indicating the builder had a right to work. Bear said that made it hard to impose the full penalty.

Mayor John Chappie made a motion for the commission to follow Carr’s recommendation and reduce the penalty to $10,000. Bear and Talham voted in favor of the proposed $10,000 fine. Chappie and Commissioner Debbie Scaccianoce voted against it.

Because the Ward 3 commission seat formerly held by Ralph Cole is currently vacant, the two opposition votes resulted in a 2-2 tie, and the motion failed without the majority support of the four commission members present.

Scaccianoce questioned the builders’ explanation for the permitting issue. She said she had a problem with a builder and contractor claiming not to know the difference between a building permit and a floodplain permit.

Chappie asked whether the Mason Martin owners were told about that day’s meeting. Carr said company representatives indicated someone would attend, but no one did.

Chappie said it would have meant a lot if someone from the company had been there to plead its case. He noted the company was told to stop work and continued anyway, which he said showed how much the company respected the stop-work order.

MIDDLE GROUND FOUND

After the first motion failed, Bear proposed a reduction that tied the penalty to the cost of the permit fees, rather than the $10,000 Carr recommended.

Bear proposed imposing a $21,477 penalty, which would be double, not triple, the original $21,477 permit fee.

Bear said doubling the permit fee could cover the city’s costs addressing the permitting issue.

Bear noted the permit fee amounts are set forth in the land development code, but the city commission has some leeway when it comes to imposing a double-fee or triple-fee permit penalty.

City Attorney Erica Augello confirmed that was the case. She said the permit fees are set by city resolution and included in the city’s land development code.

“The permit fees are the permit fees,” Augello said. “But I think what Commissioner Bear is talking about is the after-the-fact penalty that is usually three times the permit fee. 

From a legal point of view, you don’t have to grant anything.”

Augello said a commission-supported penalty reduction had a defensible rationale, but granting such penalty relief acknowledges some city responsibility for the permitting issue.

“I think that’s a justifiable basis for the reduction from a legal perspective,” she said of the penalty being reduced.

The commission voted 4-0 in favor of the $21,477 penalty. Imposing a triple-fee penalty would have increased the after-the-fact building permit fee to $64,431.

When issued, the after-the-fact building permit will allow the construction project to resume.

SHARED BLAME

When contacted on Nov. 21, Agnelli declined comment on the commission’s decision, other than to say he would be contacting his attorney.

“The city has liability in this,” he said in regard to the permitting issue.

When speaking to The Sun in October, Agnelli said, “We believe both parties share the blame. Ben came in after this issue began and it’s not on him. The city should have caught this during the first inspection. I would not have started this job knowing I didn’t have a permit.”

Related coverage: City and builder working to resolve permitting issue