FDOT stresses patience during sidewalk replacement project

FDOT stresses patience during sidewalk replacement project

BRADENTON BEACH – The Florida Department of Transportation’s installation of a brick paver sidewalk along Gulf Drive North was temporarily complicated by a broken water pipe.

The construction accident occurred on the morning of Thursday, Oct. 21. The broken pipe contributed to the ongoing Gulf Drive traffic delays associated with the FDOT-funded sidewalk replacement project.

The broken water pipe also impacted water pressure for some Bradenton Beach residents. During Thursday afternoon’s Bradenton Beach City Commission meeting, Commissioner Ralph Cole said his residential water service was impacted by the broken pipe.

At 4 p.m. Thursday afternoon, FDOT Community Outreach Manager Barbara Catlin responded to an email inquiry from The Sun.

“The contractor hit a water source and it has been repaired. This can happen in construction environments. Teams were in place to supervise this situation, including FDOT, Manatee County and the city of Bradenton Beach. Water will return to full pressure now,” Catlin stated in her email.

City Attorney Ricinda Perry also expressed concerns about project-related signage impeding sidewalks and bike lanes and she asked that the signs be repositioned accordingly.

FDOT stresses patience during sidewalk replacement project
Concerns have been expressed about project signage impeding sidewalks and bike lanes. – Joe Hendricks | Sun

Ongoing concerns

City officials continue to express concerns about FDOT’s sidewalk replacement project. The concerns pertain in part to the use of oversized brick pavers and the manner in which they are being installed along Gulf Drive North, from Ninth Street North to the S-curve near the southern end of Avenue C.

City officials are also concerned about FDOT’s expectation that the city will maintain and repair the brick paver sidewalk after the state-funded installation is completed.
On Wednesday, Oct. 13, Bradenton Beach Public Works Director Tom Woodard shared the city’s concerns with FDOT Construction Project Administrator Christopher McInnis.

In his email, Woodard stated, “I understand the difficulties of your position and with the project environment, but on behalf of the city commission, residents and visitors, I need to again express concerns with the installation of the brick paver sidewalk. In our estimation, there are numerous tripping hazards, uneven surfaces and (we) believe that the asphalt fill on the borders is too thin to last and will ultimately become another hazard for walkers and bikers, as well as a constant maintenance issue/expense for the city.

FDOT stresses patience during sidewalk replacement project
Safety concerns and solutions have been discussed regarding the currently uneven sidewalks. – Joe Hendricks | Sun

“I have been informed that the city is not willing to accept the responsibility/liability for the sidewalk if what currently exists is the finished product. For the city to be willing to accept the maintenance and responsibility, FDOT will need to contact the city’s legal department to see if the commission is willing/able to adjust the agreement,” Woodard wrote.

On Thursday, Oct. 14, Woodard received an email response from FDOT Operations Center Engineer Trisha Hartzell.

In her response, Hartzell stated, “Thank you for your email expressing your concerns on the paver project initiated by the city of Bradenton Beach, funded and constructed by the department and maintained by the city of Bradenton Beach. We respectfully ask that you please be patient with us during the construction phases of this project, as no portion within the limits of construction is at 100% final completion. There is still a lot of work left on this project.

“A little education about the installation process: It is being performed in multiple layers and after the pavers are installed they are being tamped down to even them out. The pavers are being installed per standard specifications and Americans with Disabilities Act (ADA) requirements, with no greater than 2% cross slope. However, the existing sidewalk is out of compliance with specs and ADA requirements. Therefore, we will also be replacing sections of the sidewalk to meet the pavers and have a smoother transition back into compliance,” Hartzell wrote.

“In reference to your comment with regards to the asphalt, again this is currently a temporary construction condition and we ask for your patience during the construction process. What you see backfilled in the asphalt is cold patch the contractor will be milling and resurfacing from the edge of the travel lane to the pavers. In the interim, a temporary condition needs to exist for safety. Originally, the Manatee County UWS plans called for their contractor to remove and replace the asphalt from the edge line to the pavers, however, we have been informed that this work was removed before the contract was finalized. Therefore, we will be adding work to this contract to leave it in an acceptable and safe condition,” Hartzell wrote.

“We will have two walk-throughs on this project before a final acceptance and transfer of maintenance takes place. The city will be invited to these walk-throughs and it is imperative that you are in attendance. This project is a partnership between the city of Bradenton Beach and FDOT and I encourage you and your team to reach out to me with any concerns so that we can discuss and address them before shedding a negative light into the community. This paver project was initiated by the city and the department came forward with the means to accomplish it. At the end of the day, we all want the same thing: a safer, more efficient product to relieve flooding issues for safety and community success,” Hartzell wrote.

Related coverage

 

FDOT sidewalk project concerns Bradenton Beach officials

FDOT sidewalk project concerns Bradenton Beach officials

FDOT sidewalk project concerns Bradenton Beach officials

BRADENTON BEACH – City officials share some lingering concerns about the permeable brick paver sidewalk the Florida Department of Transportation (FDOT) is installing along Gulf Drive.

The concerns include potential safety and tripping hazards and the city’s future liability and maintenance responsibilities.

Funded and supervised by FDOT, the sidewalk project calls for the replacement of the existing concrete sidewalk along Gulf Drive North, from Ninth Street North to the s-curve near the south end of Avenue C.

The larger, permeable pavers being used for the FDOT sidewalk project are approximately a foot thick and are much thicker than standard-sized brick pavers. It’s hoped the thicker pavers will provide greater stability and durability alongside the heavily traveled state road and state-owned right of way.

FDOT sidewalk project concerns Bradenton Beach officials
In May, a comparative example of the larger-sized brick pavers (on the left) was provided to city commission members. – Joe Hendricks | Sun

According to the post-project maintenance agreement with FDOT which Mayor John Chappie, City Clerk Terri Sanclemente and City Attorney Ricinda Perry signed in September 2020, the city will be responsible for the future maintenance of the FDOT-installed sidewalk.

According to the agreement, “It is understood and agreed by the parties that upon completion of the project, the local agency (the city of Bradenton Beach) shall be responsible, at its costs, for maintenance of said project. Maintenance items to be maintained by the local agency shall include, but not be limited to: removal of graffiti, pervious pavers and aesthetic features. The local agency shall maintain pavement surfaces free from residue accumulation, algae, vegetation and other slip or trip hazards. The local agency shall sweep, vacuum, edge and provide weed control along the project corridor from 10th Street to Avenue C, only at the permeable brick paver locations. The local agency shall ensure the safety of the public by repairing shifted pavers and maintaining the permeable brick pavers and any other safety features within the project corridor. The local agency shall maintain and repair the permeable brick pavers at its sole cost and expense, in a good and workmanlike manner and with reasonable care.”

Before entering into the agreement with FDOT, the mayor, city commissioners, public works director and city attorney expressed concerns about the use of the oversized pavers and the ongoing maintenance responsibilities and costs to be incurred by the city.

Chappie addressed the city’s ongoing concerns during the Thursday, Oct. 7 city commission meeting.

“It’s not what we expected. We don’t really have high expectations of how successful it’s going to be. We have put FDOT on notice of our grave concerns with regards to safety, the tripping hazards and how it’s being installed. We don’t want to increase any extra liability on our city for something FDOT is doing,” Chappie told the commission.

“I worry about pavers. You are going to trip on pavers. They can’t be even all the time,” City Commissioner Jan Vosburgh added.

“It’s their right of way, their sidewalk,” Chappie responded.

FDOT sidewalk project concerns Bradenton Beach officials
Mayor John Chappie is among those concerned about the new sidewalk being installed by FDOT. – Joe Hendricks | Sun

Chappie noted Public Works Director Tom Woodard had communicated the city’s concerns to FDOT officials. Woodard emailed FDOT Construction Project Administrator Chris McInnis on Monday, Oct. 4.

“I just wanted to touch base with you about the sidewalk replacement/brick installation project, as a few concerns with the installation have been brought to my attention. I just need to be sure that correct installation oversight and inspection is taking place? The brick appears to be wavy with some potential trip hazards. I’m sure the abundant groundwater and with the weight/size of the bricks it makes for a difficult installation, but we need to be sure we get the best end result possible,” Woodard stated in his email.

In the response he sent Woodard that day, McInnis wrote, “The installation of the pavers are being installed per plan and manufacturer specifications. The contractor is doing their best to provide a quality product. The contractor and I have been working close together in making sure that all the concerns of the department, county and Bradenton Beach are mediated. Any and all concerns regarding the safety of the finished product will be addressed.”

After receiving a copy of that email exchange, Chappie sent Woodard an email that said, “Thanks for putting FDOT on notice of our grave safety concerns. This type of design, using blocks, have inherent challenges with installation. Thanks for staying on top of this project.”