Mason Martin Builders selected to build pier restaurant and bait shop

Mason Martin Builders selected to build pier restaurant and bait shop

ANNA MARIA – Frank Agnelli’s Mason Martin Builders is the city’s top choice to construct the restaurant and bait shop at the T-end of the new Anna Maria City Pier.

Based on Mayor Dan Murphy’s recommendation, city commissioners voted 5-0 in support of the mayor entering into contract discussions with Mason Martin Builders’ owner Frank Agnelli. That vote occurred during a six-minute emergency commission meeting on Thursday, June 6.

The city received four bids in response to its recent invitation to bid and request for proposals (RFP). Mason Martin Builders submitted the lowest bid at $1.04 million. D.L Porter Constructors’ bid was second lowest at $1.486 million, followed by the Burke Construction Group at $1.609 million and Jon F. Swift Construction at $1.688 million.

City Clerk LeAnne Addy provided the commissioners with sealed copies of the bid proposals during the previous week’s emergency meeting and the bids were made public during Thursday’s meeting.

Before making his recommendation, Murphy said the RFP states the contract will be awarded to the lowest responsible bidder as determined by the city to be in the city’s best interests.

Murphy said he defined the best interests of the city as having the ability to quickly get started, having the ability to complete the project and a reputation for completing projects, having a vested interest in the project and taking into consideration the city’s interests at every step of the way.

“Having taken all that into consideration, I can give you a recommendation. My recommendation is that we go with Mason Martin,” Murphy said.

Mason Martin Builders selected to build pier restaurant and bait shop
Mason Martin Builders owner Frank Agnelli was pleased by the commission’s decision. – Joe Hendricks | Sun

Commissioner Doug Copeland and commission chair Brian Seymour said they supported the mayor’s recommendation.

“They came up number one in my choices. They’re local, all the subs will be local and it makes sense to me,” Seymour said.

Commissioner Carol Carter said Mason Martin appeared to have the most thoroughly thought out response. Seymour agreed and said that helped him make his decision.

Copeland made the motion to authorize Murphy to attempt to negotiate a contract with Mason Martin and the commission unanimously supported that motion.

The negotiated contract terms must be brought back to the commission for final approval.

If those negotiations prove unsuccessful, Murphy would then seek commission authorization to attempt to negotiate a contract with the commission’s next highest-ranked firm, which was not determined at Thursday’s meeting.

Post-meeting comments

Last summer, Agnelli and his crew removed the engraved wooden planks from the old pier so they could be returned to those who previously purchased them from a third-party. Agnelli did that at no cost to the city. The unclaimed planks will be repurposed as memorial walls or for some other public use.

After Thursday’s meeting, Agnelli commented on the commission’s decision.

“I’m glad I got the job, I’m glad this gets to stay local and we’ll get it done quicker than anyone else. It’ll be great to have my name on it for my kids to see, so I’m pretty happy about that too,” he said.

Murphy congratulated Agnelli and said, “I look forward to working with him. We know each other pretty well and I look forward to a good relationship and a successful conclusion.”

Regarding last year’s plank removals, Murphy said Agnelli did it out of the goodness of his heart.

Murphy said it was too early to know exactly when the construction of the restaurant and bait shop spaces will begin.

Mason Martin Builders selected to build pier restaurant and bait shop
I+iconSoutheast continues its construction of the primary pier structure, decking and T-end deck area. – Joe Hendricks | Sun

I+icon’s construction of the pier structure, decking and T-end deck area is scheduled for completion on Aug. 27. I+icon did not bid on the construction of the restaurant and bait shop spaces to be built according to design plans created by architect Barron Schimberg.

Murphy said he expects to meet soon with current pier tenant Mario Schoenfelder regarding his financial contribution to the interior build-out of the restaurant and bait shop. Schoenfelder’s current pier lease with the city expires in December 2020 and he is being asked to contribute to the pier project if wants to remain on the pier beyond that.

Murphy estimated the final cost of the entire pier project will now exceed $5 million.

Related coverage

Pier building bids received but not revealed

Last pier piling driven

Pier pavilion closing temporarily

Anna Maria Pier Demolition

Speeler and Associates selected to demolish Anna Maria City Pier

ANNA MARIA – The city now has a firm under contract to demolish the Anna Maria City Pier.

On Wednesday, June 6, the Anna Maria Commission voted 4-1 in favor of Mayor Dan Murphy being authorized to execute a $732,000 contract with Largo-based Speeler & Associates.

Speeler & Associates was the city’s second-highest ranked demolition bidder. Murphy entered into fact-finding conversations with the firm earlier this week after he and Sully’s Quality Projects owner Sean Sullivan were unable to agree on payment terms for a proposed $673,530 demolition contract.

Sullivan wanted a $53,822 payment before mobilizing to the pier worksite. Murphy and the commission deemed those terms unacceptable and on Monday, June 4, Murphy was authorized to begin discussions with Speeler & Associates.

“This contract has been reviewed by our city attorney. We both feel very comfortable that this is a good and fair and equitable contract,” Murphy said. “You’ll see progress here shortly.”

The contract was signed Wednesday. It calls for an initial payment of $100,000 after the company has completely mobilized at the pier worksite by the end of June. The pier will be fenced off and barge-based cranes will be stationed at the end of the pier.

The contract calls for a total of four payment phases including a final payment of $109,000 when the work is finished.

Speeler & Associates has until June 11 to secure a performance bond that guarantees the firm fulfills its contract.

The contract calls for the pier demolition to completed on or before Sept. 30. The contract includes a $500 per day penalty for each day the work exceeds the agreed-upon completion date.

“They do anticipate that they can do it sooner than that and because of these payments they’d like to do it sooner than that. That’s the carrot on a stick,” Murphy said of the demolition timeline.

Murphy said one clause was added to the contract regarding any additional work requested by the city beyond what Speeler & Associates included in its bid document response to the city’s request for proposals.

“If we come up with something extra we want them to do outside the bid document, we’re going to pay extra for it. That seems only logical,” Murphy said.

When it was time to vote, Commissioner Dale Woodland opposed with additional comment Commissioner Carol Carter’s motion to authorize Murphy to execute the contract with Speeler & Associates.

During the commission’s May 18 pier meeting, Woodland said he could not support the selection of a demolition firm because he does not support the demolition of the pier. He believes the existing pier and pier structures should be repaired and/or rehabilitated.

Pier planks

Later in the week, Murphy said local contractor Frank Agnelli and his crew from Agnelli Pools Construction and Mason Martin Builders are scheduled to begin pulling the engraved pier planks in late June.

Some of the engraved pier planks that were purchased from a non-city entity will be returned to those who formally requested their return. The unclaimed planks will be stored by Agnelli and used later by the city to build memorial walls at City Pier Park and in the historical park near the Anna Maria Island Historical Society Museum.

Murphy recently said he anticipates the requested planks to be available for pick up in early July.

The pier has been closed since September due to Hurricane Irma damage sustained to the T-end decking, restaurant space and bait shop. The new $4.5 million pier, restaurant space and bait shop are slated for completion and reopening in late 2019.

New Anna Maria City Pier
The new pier will feature a new bait shop and a new restaurant space. – Schimberg Group | Submitted