Anna Maria discusses mangrove regulations

Anna Maria considers regulating mangroves

ANNA MARIA – Building Depart­ment General Manager Dean Jones is leading the city’s efforts to join Holmes Beach, Bradenton Beach and Longboat Key in adopting and self-enforcing local mangrove regulations.

The multi-municipality regulatory efforts were first discussed during the April 17 Coalition of Barrier Island Elected Officials (CBIEO) meeting in Longboat Key. During that meeting, Anna Maria Mayor Dan Murphy proposed that the four barrier island municipalities work together to establish a local mangrove regulation program that would supersede the regulations currently enacted and enforced by the Florida Department of Environmental Protection (FDEP).

Jones also attended the meeting and on April 25, at Murphy’s request, he provided the Anna Maria City Commission with an overview of the mangrove regulation and enforce­ment efforts to be pursued.

Anna Maria discusses mangrove regulations
Building Department General Manager Dean Jones is leading Anna Maria’s pursuit of local mangrove regulations. – Joe Hendricks | Sun

Jones’ presentation referenced a much-publicized mangrove removal event that occurred in late 2023 at a canal-side home at 111 Gull Drive in Anna Maria. The presentation included photos of the property before and after the mangroves were removed to make way for a new seawall.

“Part of what brought this process about was the fact that mangroves had been destroyed by a homeowner from out of state that felt they needed a seawall and didn’t really understand how important mangroves are to our ecosystem,” Jones said.

Another presentation slide listed the five Florida counties, one Florida city and one Florida town that have enacted their own local mangrove regulation and enforcement programs since 1996. Jones said of those seven, only Sarasota County’s mangrove program remains active.

Commissioner Charlie Salem asked Jones why the other mangrove enforcement programs faded away.

Jones said some people he spoke with didn’t even know who started their local mangrove programs and whether they ended due to a lack of resources or a lack of interest.

“The good thing is DEP will allow us to enforce our own mangrove ordinances, but we have to make sure we have the resources to do so,” Jones said.

Jones said he’ll be working in unison with Holmes Beach Planning and Zoning Administrator Chad Minor, Bradenton Beach Building Official Darin Cushing and Longboat Key Planning, Zoning and Building Director Allen Parsons.

Regarding FDEP requirements for local mangrove enforcement, one presentation slide said, “To receive delegation, a local govern­ment must demonstrate that it has sufficient resources and procedures for the adequate administration and enforcement of a delegated mangrove-regulatory program. This does not preclude a delegated local government from imposing stricter substantive standards or more demanding procedural requirements for mangrove trimming or alteration outside of riparian mangrove fringe areas.”

The presentation listed several next steps to be taken. Interlocal agreements must be established with all four participating municipalities and uniform guidelines must be adopted to provide continuity regard­ing administration and enforcement, including the fines and penalties levied on violators.

The municipalities must meet educational requirements and administrative guidelines and enforcement and communication protocols must be developed between the four municipalities to help intercept possible violations before they occur, or in the early stages of the occurrence.

“We need to have continuity across all the cities if we’re going to make this work,” Jones said. “Mangroves are a huge part of our ecosystem. When we remove them, bad things happen. The water gets worse and the wildlife goes away. We have the ability to protect our mangroves locally. We don’t have to let what happened at 111 Gull happen again. We can have some control over it.”

After noting that he also attended the CBIEO meeting, Salem thanked Murphy for his leadership and he suggested gathering more information about Sarasota County’s mangrove regulations and enforcement efforts.

During public input, Anna Maria resident Wayne Patterson thanked Jones and said, “I live right around the corner from that last decimated mangrove effort.” He asked how the city regulates mangroves in conjunction with property owners’ desire to install seawalls.

Commissioner Mark Short noted the city commission adopted a seawall ordinance a couple of years ago that states any new seawall installed must be installed landward of any mangroves that border the property – and doing so doesn’t reduce the total lot coverage allowed.

Patterson noted that didn’t happen at 111 Gull.

“They were removed before the permit for the seawall was applied for,” Short said. “Currently the city has no remedies. We always thought DEP would be the ones to remedy the situation. In my opinion, they’re not doing their job.”

Murphy then said, “At 111 Gull he had a permit from DEP. He did not have a seawall permit yet, but he had a permit to pull out all those mangroves. That’s what we’re trying to do here to preclude that from happening again. Otherwise, it’s going to keep happen­ing,” Murphy said.

“Until we have local control,” Jones added.

Salem then said, “Because DEP doesn’t recognize man-made canals as part of this protection, that’s why they were allowed to remove those mangroves. We would be able to prohibit that kind of removal in those man-made canals.”

When asked what happens if one or more of the barrier island municipalities can’t agree on the mangrove regula­tions and enforcement measures later proposed, Murphy said, “We move right on. We need to get something done. In that meeting there was a pretty thorough understanding of what we needed to do and why we needed to do it. If somebody decides to back out, they’re on their own and the other cities will move forward.”

PAST PRESENTATION

This is not the first time the city of Anna Maria has inquired about estab­lishing a local mangrove enforcement program. In 2020, FDEP representa­tive Hannah Westervelt and the Anna Maria Commission participated in a mangrove trimming workshop.

During the workshop, Westervelt said, “Any local government can get the delegation of authority to regulate trim­ming and alteration of mangroves, but a local agency has to demonstrate they have the resources and the procedures in place. To establish that local program, you have to submit a written request for delegation to the department.”

Related coverage: 

Mayors propose to regulate mangroves

Feds issue approval for mangrove removal

Mangrove removal under Army Corps review

Mangrove removal under Army Corps review

ANNA MARIA – Nearly two months after a contractor destroyed 67 feet of mangroves to build a seawall at 111 Gull Drive without all the required approvals, one of the permitting entities – the U.S. Army Corps of Engineers (USACE) – has still not decided about issuing a permit.

USACE spokesperson David Ruderman wrote in a Feb. 8 email to The Sun, “The Corps permit section is continuing consultation with National Marine and Fisheries Service to resolve issues related to the property owner’s permit application.”

Without specifying what the issues are, he wrote that the application decision is expected “in the near future.”

The mangroves were removed in December despite a City of Anna Maria stop work order, according to a Dec. 18 email to The Sun from Mayor Dan Murphy.

“The city received a complaint from a resident on Dec. 4, 2023, regarding the extensive removal and alteration of mangroves at 111 Gull Drive,” Murphy wrote on Dec. 18. “City staff visited the property and confirmed mangroves had been removed and fill dirt had been added in its place. The scope of work is proposed by building permit ACC22-000153 which has not been issued and thus, is not permitted to commence.”

Murphy wrote the city posted a stop work order on the property on Dec. 6 and on Dec. 13 city staff received several complaints that mangroves had been removed once again.

“City staff visited the site on Dec. 13, 2023 and observed workers actively removing mangroves,” Murphy wrote.

Murphy also wrote that the stop work order had been removed from the property and was reposted by city staff.

In a Dec. 19 email to The Sun, Murphy identified Mason Martin LLC as the contractor that had removed the mangroves.

An FDEP seawall exemption had been granted to Mason Martin LLC for mangrove removal. FDEP inspectors visited the property on Dec. 22 in response to complaints.

“A complaint inspection conducted on Dec. 22, 2023 revealed that prior authorization was received from the Department in a seawall exemption (File No.: 41-0422234-001-EE), to construct approximately 116 linear feet of seawall,” according to the FDEP inspection report. “The inspection revealed that construction had commenced and a portion of the mangroves on the property were removed within the exempt activity’s footprint. Erosion control devices were installed upon request after the inspection. In addition, the Department notified the property owner that they should continue to coordinate with USACE and to not continue construction until a USACE authorization is obtained.”

Mangroves removed before protective barrier installed

Mangroves removed before protective barrier installed

ANNA MARIA – More than three weeks after the removal of mangroves at 111 Gull Drive, a required protective water barrier was placed at the site, according to neighbors.

The Florida Department of Environmental Protection (FDEP) noted the absence of the barrier in its investigation of the mangrove removal on Dec. 13. FDEP’s Heather McClurg emailed others in the agency saying in part, “After viewing the photos though (of the property at 111 Gull Drive), I did note that they do not have proper BMP’s deployed and wanted to forward this over to compliance for review.”

A BMP (Best Management Practice) is a method used to prevent or control stormwater runoff and the discharge of pollutants, including sediment, into local waterbodies, according to the Environmental Protection Agency.

The mangroves at 111 Gull Drive, a canal-front home under construction, were removed in early December, according to a complaint received by the city, which posted a stop work order on Dec. 6. Neighbors complained again on Dec. 13 that more mangroves were removed.

Federal, state and local officials are investigating.

The protective material was installed on Dec. 28, according to Ronnie Leto, a neighbor with a view of the property.

On The Sun Facebook page, Jane Ingalls posted an aerial photo of the property at 111 Gull Drive showing the mangroves prior to their removal. In that photo, lush mangroves were present behind the canal front home. A second photo posted by Ingalls shows what she called a side view of the former mangroves at 111 Gull Drive in August. No mangroves remain at the property.

The FDEP previously issued a seawall permit exemption for a limited amount of mangrove removal to contractor Mason Martin LLC, but FDEP spokesperson Brian Humphreys said on Dec. 22 that the agency was investigating complaints about excessive mangrove removal and planned a site visit.

It was reported on Dec. 23 to The Sun by a neighbor that FDEP investigators conducted a site visit at the property. That visit has been unconfirmed by FDEP.

The Sun has requested a follow-up report from the agency, but it was not received by press time.