HomeCommunity NewsBradenton BeachRocks beat out concrete...

Rocks beat out concrete in shoreline project

BRADENTON BEACH – City officials have made significant changes to the plans for a shoreline resiliency project along Bay Drive South from the south side of the Bradenton Beach Pier to Fifth Street South.

The revised plans no longer call for a concrete resiliency wall and now propose using riprap barriers made of rocks and sand instead. The revised plans also eliminate the proposed installation of reef balls in Sarasota Bay across the street from the Old Bridge Village condominiums.

The project is being designed and engineered by the Tampa-based Environmental Science Associates (ESA) firm, with senior scientist Brett Solomon and engineer Bryan Flynn working closely with city officials.

Shoreline project no longer includes concrete wall
The proposed project area includes the Bradenton Beach Pier and the Bridge Tender Inn shoreline. – ESA | Submitted

In an effort to address king tides, rising tides and future sea level rise, the Bradenton Beach City Commission and the Bradenton Beach Community Redevelopment Agency (CRA) are jointly pursuing the resiliency project that city attorney and CRA liaison Ricinda Perry says has evolved into a shoreline renourishment project.

ESA presented the 30% completed plans in early January. In late January, Solomon and Flynn conducted publicly noticed on-site meetings with city officials and potentially impacted property owners.

During the March 17 joint city commission/CRA meeting, Solomon and Flynn presented the 60% completed plans that included revisions based on input received from city officials and potentially impacted property owners.

Wall removed

The 30% completed plans proposed installing a concrete wall and/or earthen berm along the Bay Drive South shoreline. That concept was met with much resistance from city officials and potentially impacted property owners.

Throughout the engineering process, city commissioner and CRA Chair Ralph Cole has expressed his desire for a shoreline project that uses natural materials as much as possible.

“We don’t want the wall. That’s pretty much what everybody’s decided. They don’t want a concrete barrier,” Cole said during the March 17 meeting.

The 60% completed plans approved by the city commission and CRA members that day no longer include a concrete wall.

Riprap

There’s already an existing riprap barrier about 2.5 feet high along the length of Fred Bartizal’s Bridge Tender Inn & Dockside Bar property. The revised plans propose extending the existing riprap 10 feet to the east and possibly raising it by another 1.5 feet to get to the 4-foot elevation recommended by ESA.

According to Perry, the proposed project would result in the extended Bridge Tender Inn shoreline having a beach-like appearance, with the rocks being covered by sand. Trees, mangroves and other erosion-controlling plants might also be placed in the expanded shoreline area.

Shoreline project no longer includes concrete wall
The coral-colored line indicates the location of the proposed riprap barrier. – ESA | Submitted

Matching riprap and a similarly extended shoreline would continue south to the small city-owned pocket park at the east end of Third Street South.

To accommodate the existing mangroves near the pocket park, a slightly elevated walkway would be installed between the landward side of the mangroves and the edge of Bay Drive South, with riprap placed under the walkway and along the mangroves and existing vegetation that already help absorb and dissipate wave energy. The existing mangroves will not be removed.

Shoreline project no longer includes concrete wall
The engineering plans propose a slightly elevated walkway alongside Bay Drive South. – Joe Hendricks | Sun

The walkway built over the riprap would continue south along Bay Drive South to Fifth Street South and Perry said Bartizal is amenable to the walkway continuing north on his property to Bridge Street.

Shoreline project no longer includes concrete wall
The riprap (illustrated in coral) and the elevated walkway (illustrated in yellow) would extend to Fifth Street South. – ESA | Submitted

“People won’t see the rocks,” Perry said of the riprap.

The revised plans propose small stairways or ramps that go up and over the riprap to provide uninterrupted access to the privately-owned docks along Bay Drive South.

Flynn said the riprap barriers could be raised in 10-15 years by adding more rocks and sand if conditions warrant doing so.

Reef balls

The 30% completed plans proposed installing reef balls in the bay across the street from the Old Bridge Village condominiums. The reef balls were proposed to dissipate incoming wave energy and reduce the amount of sand and sediment that washes away from the shoreline. Some condo owners expressed concern about aesthetics and visibility.

Shoreline project no longer includes concrete wall
In late January, Old Bridge Village condo owners used this prop to express their concerns about the anticipated size and visual impact of the proposed reef balls. – Joe Hendricks | Sun

The revised 60% completed plans now propose installing reef balls only along the south side of the Bridge Street Pier and clock tower walkway. Reef balls would not be placed near the condos.

Shoreline project no longer includes concrete wall
The blue circles indicate where reef balls would be placed near the Bradenton Beach Pier. – ESA | Submitted

Made of oyster shells, smaller oyster bags and oyster pyramids would be placed in the water throughout the project area to help dissipate wave energy and reduce sediment washout.

Public input

During public input at the recent joint meeting, Bartizal and residential property owners Krista Czajkowski and Marvin Taake expressed support for the revised plans.

Czajkowski said her biggest concern was maintaining the ability to install or replace boat lifts and docks. Flynn said the riprap barrier would not negatively impact boat lifts, docks or navigation.

Taake said drainage and flooding were his biggest concerns. Flynn said the proposed project will include drainage elements that improve the flow of rainwater to the outfalls that discharge into the bay.

“I think it’s win-win for everybody,” Bartizal said.

Funding

The design and engineering phase is being funded with a $92,433 resiliency grant from the Florida Department of Environmental Protection (FDEP). For state and federal permitting purposes, the design and engineering must be 100% completed in August.

The current grant does not include funds to construct the engineered project and no cost estimates to construct the proposed project have been provided. During the joint meeting, ESA and Perry were authorized to work together to pursue additional FDEP resiliency grants to construct the fully engineered and shovel-ready project. There is currently no estimated timeline as to when the proposed project would be constructed.

Most Popular

More from Author

AMI community ‘rises up’ for River

ANNA MARIA – The Anna Maria Island commu­nity is coming out...

Holmes Beach ferry stop discussed

HOLMES BEACH – City elected officials are discussing with Manatee County...

Pedicini consulting for Satcher, Van Ostenbridge, Turner

MANATEE COUNTY – During a recent Supervisor of Elections debate, candidate...

Candidates Farrington, Satcher answer voter questions

MANATEE COUNTY – Manatee County Supervisor of Elections candidates Scott Farrington...

City presents 2024-25 budget

HOLMES BEACH – City leaders are working to keep property taxes as low as possible despite property values increasing an estimated 11.8%. To do that, they’re planning to keep the millage rate at 2.05 mills for the coming fiscal year and cut expenses from the proposed 2024-25...

Settlement reached in Piney Point litigation

PALMETTO - Prompted by a 2021 lawsuit by multiple conservation groups, the Florida Department of Environmental Protection (FDEP) has agreed to allow more oversight of discharges from the Piney Point phosphate facility. The settlement agreement also establishes enforceable limits on pollution discharged into Tampa Bay and provides for...

AMI community ‘rises up’ for River

ANNA MARIA – The Anna Maria Island commu­nity is coming out in sup­port of Mackenzie Morgan, Jonathan Anasis, their 3 1/2-month-old son, River Anasis, and their young daughter, Vayda Anasis. On July 13, the Rise Up for River Benefit: A Community Rally for Hope and Healing event took...

Holmes Beach ferry stop discussed

HOLMES BEACH – City elected officials are discussing with Manatee County tourism officials whether to add a Gulf Island Ferry stop in Holmes Beach. Currently, Manatee County’s contracted ferry service stops in downtown Bradenton, the Anna Maria City Pier and the Bradenton Beach Pier, with an additional stop...

Pedicini consulting for Satcher, Van Ostenbridge, Turner

MANATEE COUNTY – During a recent Supervisor of Elections debate, candidate James Satcher refused to acknowledge he’s us­ing Anthony Pedicini as his political consultant. Manatee County Commission candidates Kevin Van Ostenbridge and Ray Turner are also utilizing the campaign consulting services of Pedicini and his Tampa-based Strategic Image...

Government calendar

Anna Maria 10005 Gulf Drive For information, call 941-708-6130 Please visit www.cityofannamaria.com or contact city hall for more information. July 18, 1 p.m. – City Commission budget meeting July 18, 2 p.m. – City Commission meeting July 24, 9 a.m. – Planning and Zoning board meeting July 25, 5 p.m. – City Commission budget...

Beach Nutz

       

Events

Wednesday, July 17 One-on-one Tech Help, Island Branch Library, 5701 Marina Drive, Holmes Beach, 2 p.m. Sharks and rays conservation research, Island Branch Library, 5701 Marina Drive, Holmes Beach, 2 p.m. Thursday, July 18 One-on-one Tech Help, Island Branch Library, 5701 Marina Drive, Holmes Beach, 10 a.m. Wild About Wildlife, Island Branch...

Bargains on the beach

Realtor.com is part of my everyday life. I check it for new listings, sold listings, open houses and sometimes just to look at the pictures on what may be an otherwise slow day. Sometimes I even learn something I didn’t know, like their recent story about the 10...

Catch and release

Taking care when we release fish we don’t intend to keep has never been more important. While most anglers are aware that fish populations are vulnerable and not the endless resource we once thought them to be, shrinking habitats and fish populations make the process all the...

Second sea turtle nests in daytime

ANNA MARIA – More than 100 beachgoers saw an uncommon sight when a nesting loggerhead sea turtle laid her eggs during the day on June 26, the second daytime nesting in a week. Anna Maria Island Turtle Watch and Shorebird Monitoring volunteers posted photos and the following on...