Increased costs anticipated for Bradenton Beach dock project

BRADENTON BEACH – Bradenton Beach’s long-delayed $119,980 floating dock project may now cost an additional $45,302 to $69,456 to complete.

On Wednesday, April 3, Police Chief and pier team facilitator Sam Speciale presented Bradenton Beach Community Redevelopment Agency (CRA) members with two dock installation estimates he received from Hecker Construction Company Operations Manager Eric Shaffer on March 25.

Hecker estimates $81,600 to install the previously-purchased floating dock components using yet-to-be-purchased wooden pilings, or $105,754 to complete the project using yet-to-be-purchased composite pilings.

These estimates took CRA members by surprise and they requested a special follow-up meeting on Wednesday, April 10. The members asked Speciale to bring back a second opinion from another engineer regarding the number of pilings needed. Speciale was also asked to bring back a second opinion from Duncan Seawall, Dock & Boat Lift regarding Hecker’s cost estimates. In 2015-16, Duncan built the Bridge Street Pier; the floating dock will be installed next to the pier.

The original $119,980 contract the CRA and Technomarine agreed to in early 2017 included $27,000 for dock installation, pilings included. Earlier this year, the CRA released Technomarine of its remaining contractual obligations due to the lengthy delays incurred.

Technomarine had already contacted Hecker Construction about serving as a dock installation subcontractor.

Until Wednesday’s meeting, CRA members assumed Hecker would install the floating dock for the $27,000 cited in the now-invalid Technomarine contract. The CRA does not currently have a new contract with Hecker or any other firm to finish the dock project.

Increased costs anticipated for Bradenton Beach dock project
The premanufactured dock sections are being stored at the Hecker Construction Company yard in Gibsonton. – City of Bradenton Beach | Submitted

The aluminum-framed, composite dock decking sections have been sitting at Hecker’s construction yard in Gibsonton since being delivered there in September. Technomarine then delivered the dock floats to Hecker on March 4. The float delivery fulfilled the contractual release agreement City Attorney Ricinda Perry and Technomarine attorney Julianne Frank negotiated in December.

A few hours after the April 3 CRA meeting ended, Speciale received an email from Shaffer that said, “Per our phone conversation, the price of $27,000 that Techno gave the city was for us just to assemble floats and deliver them to the job site. Technomarine never spoke to us about the pilings or anything else to do with the project.”

More money

Hecker’s $81,600 estimate includes $37,000 to provide and install 36 PVC-wrapped wooden pilings and an additional $17,800 to provide and install the additional hoop brackets and rollers needed to attach the dock sections to the wood pilings.

Hecker’s $105,754 estimate includes $67,704 to provide and install 25 composite pilings and an additional $11,250 for the hoop brackets and rollers.

Both Hecker estimates include $20,000 to attach the floats to the decking, $2,800 to remove the existing pilings, $2,000 for mobilization and demobilization and $2,000 to transport the floats to the pier job site.

Increased costs anticipated for Bradenton Beach dock project
Police Chief Sam Speciale, Chad Kelly and Eric Shaffer from the Hecker Construction Company and Community Redevelopment Agency chairman Ralph Cole visited the pier on March 14. – Sherman Baldwin | Submitted

During the April 3 meeting, Speciale cited financial figures provided by City Treasurer Shayne Thompson. According to Thompson, the CRA paid Technomarine $83,682 of the $119,980 agreed to in 2017. This leaves $36,298 in remaining budgeted project funds.

As part of its 50 percent cost-sharing agreement with Manatee County, the CRA has received $41,841 in county reimbursements. In March, the CRA and the county extended that interlocal funding agreement until year’s end.

Speciale told CRA members the county originally agreed to contribute up to $125,000 for a project not to exceed $250,000. Perry questioned whether the county is willing to reimburse the CRA for the additional costs now being discussed. She suggested asking the county’s engineer to review the engineering work Clarsen Consulting Engineering did on Hecker’s behalf.

On Feb. 6, CRA members discussed but never formally approved a $9,200 estimate from Hecker Construction for engineering and permitting services. According to Thompson, the CRA has not yet been invoiced for those services.

Speciale said if wood pilings are used, Hecker’s engineer calls for a piling every five feet. Speciale said Building Official Steve Gilbert questions whether Hecker’s engineer is “over-engineering” the number of pilings needed.

Speciale said he was told the piling requirements increased after Hurricane Irma hit in September 2017, but he did not specify which agency or building code now requires more pilings than would have been required when the project was contracted in 2017.

On Friday, Gilbert said he’s not aware of any changes to the Florida Building Code that would require more pilings. On Friday, Perry said she was not aware of any new engineering requirements imposed by the Federal Emergency Management Agency or the Florida Department of Environmental Protection.

“This issue concerns me,” Perry said.

The packet for the April 10 CRA meeting includes two proposed budget amendment requests. If approved, the proposed $45,302 CRA budget amendment would cover the additional cost to complete the dock project using wooden pilings. The proposed $69,456 budget amendment would cover the additional cost to complete the project using composite pilings.

Increased costs anticipated for Bradenton Beach dock project
What remained of the previous storm-damaged floating dock was removed in August 2017. – Joe Hendricks | Sun

Most Popular

More from Author

AMI community ‘rises up’ for River

ANNA MARIA – The Anna Maria Island commu­nity is coming out...

Holmes Beach ferry stop discussed

HOLMES BEACH – City elected officials are discussing with Manatee County...

Pedicini consulting for Satcher, Van Ostenbridge, Turner

MANATEE COUNTY – During a recent Supervisor of Elections debate, candidate...

Candidates Farrington, Satcher answer voter questions

MANATEE COUNTY – Manatee County Supervisor of Elections candidates Scott Farrington...

City presents 2024-25 budget

HOLMES BEACH – City leaders are working to keep property taxes as low as possible despite property values increasing an estimated 11.8%. To do that, they’re planning to keep the millage rate at 2.05 mills for the coming fiscal year and cut expenses from the proposed 2024-25...

Settlement reached in Piney Point litigation

PALMETTO - Prompted by a 2021 lawsuit by multiple conservation groups, the Florida Department of Environmental Protection (FDEP) has agreed to allow more oversight of discharges from the Piney Point phosphate facility. The settlement agreement also establishes enforceable limits on pollution discharged into Tampa Bay and provides for...

AMI community ‘rises up’ for River

ANNA MARIA – The Anna Maria Island commu­nity is coming out in sup­port of Mackenzie Morgan, Jonathan Anasis, their 3 1/2-month-old son, River Anasis, and their young daughter, Vayda Anasis. On July 13, the Rise Up for River Benefit: A Community Rally for Hope and Healing event took...

Holmes Beach ferry stop discussed

HOLMES BEACH – City elected officials are discussing with Manatee County tourism officials whether to add a Gulf Island Ferry stop in Holmes Beach. Currently, Manatee County’s contracted ferry service stops in downtown Bradenton, the Anna Maria City Pier and the Bradenton Beach Pier, with an additional stop...

Pedicini consulting for Satcher, Van Ostenbridge, Turner

MANATEE COUNTY – During a recent Supervisor of Elections debate, candidate James Satcher refused to acknowledge he’s us­ing Anthony Pedicini as his political consultant. Manatee County Commission candidates Kevin Van Ostenbridge and Ray Turner are also utilizing the campaign consulting services of Pedicini and his Tampa-based Strategic Image...

Government calendar

Anna Maria 10005 Gulf Drive For information, call 941-708-6130 Please visit www.cityofannamaria.com or contact city hall for more information. July 18, 1 p.m. – City Commission budget meeting July 18, 2 p.m. – City Commission meeting July 24, 9 a.m. – Planning and Zoning board meeting July 25, 5 p.m. – City Commission budget...

Beach Nutz

       

Events

Wednesday, July 17 One-on-one Tech Help, Island Branch Library, 5701 Marina Drive, Holmes Beach, 2 p.m. Sharks and rays conservation research, Island Branch Library, 5701 Marina Drive, Holmes Beach, 2 p.m. Thursday, July 18 One-on-one Tech Help, Island Branch Library, 5701 Marina Drive, Holmes Beach, 10 a.m. Wild About Wildlife, Island Branch...

Bargains on the beach

Realtor.com is part of my everyday life. I check it for new listings, sold listings, open houses and sometimes just to look at the pictures on what may be an otherwise slow day. Sometimes I even learn something I didn’t know, like their recent story about the 10...

Catch and release

Taking care when we release fish we don’t intend to keep has never been more important. While most anglers are aware that fish populations are vulnerable and not the endless resource we once thought them to be, shrinking habitats and fish populations make the process all the...

Second sea turtle nests in daytime

ANNA MARIA – More than 100 beachgoers saw an uncommon sight when a nesting loggerhead sea turtle laid her eggs during the day on June 26, the second daytime nesting in a week. Anna Maria Island Turtle Watch and Shorebird Monitoring volunteers posted photos and the following on...