HomeCommunity NewsAnna MariaMayor provides pier construction...

Mayor provides pier construction update

ANNA MARIA – On Friday afternoon, Mayor Dan Murphy provided Manatee County Senior Administrative Specialist Monica Luff with an update on the construction of the new Anna Maria City Pier being built by i+iconSoutheast.

The construction update was requested by Luff, who works with the Bradenton Area Convention and Visitors Bureau and the Tourist Development Council. Both governmental entities answer to Manatee County’s Board of County Commissioners.

According to Murphy, the pier project’s total anticipated cost is approximately $4.8 million. In 2018, the county commission committed $1.5 million to the project using funds generated by the county’s 5 percent tourist tax. The county commission also allocated an additional $330,000 in surplus beach concession revenues for the project. The county’s funding commitments equate to approximately 37 percent of the total anticipated project costs.

In his Friday, Feb. 22, update to Luff, Murphy wrote, “The status of the Anna Maria City Pier project is as follows:

  • We are in the pile driving phase of construction.
  • As of today, all 70 piles for the T-end of the pier have been driven. The T-end supports both the restaurant and bait shop;
  • The T-end piles are 50’ long by 14” in diameter, each weighing 5,000 lbs.;
  • There are approximately 134 more pilings to go for the walkway leading out to the pier;
  • On average, seven piles are driven each day. Weather permitting, the contractor works six days per week;
  • All piles and equipment are transported by barge from St. Pete. and/or Tampa to Anna Maria so as to alleviate traffic congestion on the Island;
  • The barge will leave Anna Maria this Monday to procure more equipment and piles, returning Thursday (2/28), weather permitting;
  • Next phase will be placing the concrete pre-cast slabs on top of the T-end pilings, building bents (deck supports) for the walk-way out and installing utilities to the pier T-end;
  • In spite of several foul weather days, the project remains on track for platform completion by August 28, 2019,” Murphy wrote.

The construction of the pier buildings will be addressed in a yet-to-be-issued request for proposals (RFP). The selected firm will then begin a subsequent and possibly congruent phase of construction once the T-end platform is completed. It is not yet known when that RFP will be issued or when that construction phase will begin and end. Murphy said previously he expects the pier to be opened to the public by year’s end.

The forthcoming RFP process is partially contingent on the negotiations between Murphy and current pier tenant Mario Schoenfelder regarding the tenant’s contributions to the project.

Murphy has suggested Schoenfelder contribute $500,000 toward the interior buildout of the restaurant and bait shop spaces. In exchange, Schoenfelder would be allowed to provide some input on the interior design and interior components. Schoenfelder’s current lease expires in December 2020.

Mayor provides pier construction update
Due to high winds and choppy seas, no pier construction work took place on Wednesday, Feb. 13. – Joe Hendricks | Sun

On Feb. 14, Murphy provided the city commission with its first update since the construction started. He said the i+iconSoutheast crew lost two days of work that week due to inclement weather and choppy seas. Murphy said the construction company feared for the safety of its employees because of the waves created by the windy conditions. A visit to the pier worksite the previous day indicated no work taking place that day.

Most Popular

More from Author

AMI community ‘rises up’ for River

ANNA MARIA – The Anna Maria Island commu­nity is coming out...

Holmes Beach ferry stop discussed

HOLMES BEACH – City elected officials are discussing with Manatee County...

Pedicini consulting for Satcher, Van Ostenbridge, Turner

MANATEE COUNTY – During a recent Supervisor of Elections debate, candidate...

Candidates Farrington, Satcher answer voter questions

MANATEE COUNTY – Manatee County Supervisor of Elections candidates Scott Farrington...

City presents 2024-25 budget

HOLMES BEACH – City leaders are working to keep property taxes as low as possible despite property values increasing an estimated 11.8%. To do that, they’re planning to keep the millage rate at 2.05 mills for the coming fiscal year and cut expenses from the proposed 2024-25...

Settlement reached in Piney Point litigation

PALMETTO - Prompted by a 2021 lawsuit by multiple conservation groups, the Florida Department of Environmental Protection (FDEP) has agreed to allow more oversight of discharges from the Piney Point phosphate facility. The settlement agreement also establishes enforceable limits on pollution discharged into Tampa Bay and provides for...

AMI community ‘rises up’ for River

ANNA MARIA – The Anna Maria Island commu­nity is coming out in sup­port of Mackenzie Morgan, Jonathan Anasis, their 3 1/2-month-old son, River Anasis, and their young daughter, Vayda Anasis. On July 13, the Rise Up for River Benefit: A Community Rally for Hope and Healing event took...

Holmes Beach ferry stop discussed

HOLMES BEACH – City elected officials are discussing with Manatee County tourism officials whether to add a Gulf Island Ferry stop in Holmes Beach. Currently, Manatee County’s contracted ferry service stops in downtown Bradenton, the Anna Maria City Pier and the Bradenton Beach Pier, with an additional stop...

Pedicini consulting for Satcher, Van Ostenbridge, Turner

MANATEE COUNTY – During a recent Supervisor of Elections debate, candidate James Satcher refused to acknowledge he’s us­ing Anthony Pedicini as his political consultant. Manatee County Commission candidates Kevin Van Ostenbridge and Ray Turner are also utilizing the campaign consulting services of Pedicini and his Tampa-based Strategic Image...

Government calendar

Anna Maria 10005 Gulf Drive For information, call 941-708-6130 Please visit www.cityofannamaria.com or contact city hall for more information. July 18, 1 p.m. – City Commission budget meeting July 18, 2 p.m. – City Commission meeting July 24, 9 a.m. – Planning and Zoning board meeting July 25, 5 p.m. – City Commission budget...

Beach Nutz

       

Events

Wednesday, July 17 One-on-one Tech Help, Island Branch Library, 5701 Marina Drive, Holmes Beach, 2 p.m. Sharks and rays conservation research, Island Branch Library, 5701 Marina Drive, Holmes Beach, 2 p.m. Thursday, July 18 One-on-one Tech Help, Island Branch Library, 5701 Marina Drive, Holmes Beach, 10 a.m. Wild About Wildlife, Island Branch...

Bargains on the beach

Realtor.com is part of my everyday life. I check it for new listings, sold listings, open houses and sometimes just to look at the pictures on what may be an otherwise slow day. Sometimes I even learn something I didn’t know, like their recent story about the 10...

Catch and release

Taking care when we release fish we don’t intend to keep has never been more important. While most anglers are aware that fish populations are vulnerable and not the endless resource we once thought them to be, shrinking habitats and fish populations make the process all the...

Second sea turtle nests in daytime

ANNA MARIA – More than 100 beachgoers saw an uncommon sight when a nesting loggerhead sea turtle laid her eggs during the day on June 26, the second daytime nesting in a week. Anna Maria Island Turtle Watch and Shorebird Monitoring volunteers posted photos and the following on...