HomeCommunity NewsAnna MariaFEMA proposes $1.37 million...

FEMA proposes $1.37 million for pier damage

ANNA MARIA – The City Commission has accepted a $1.37 million staff recommendation from the Federal Emergency Management Agency (FEMA) that would help fund the construction of a new city pier.

During a special commission meeting on Wednesday, Aug. 29, Mayor Dan Murphy presented the FEMA recommendation for the commission to approve or reject. Murphy said the commission could challenge the FEMA offer in hopes of getting an extra $100,000 or $200,000, but he recommended accepting the offer.

Murphy said the city submitted to FEMA a $1.8 million estimate for damages the pier sustained last September during Hurricane Irma – damages that occurred when the aging pier was already slated for rehabilitation within five years.

The damage included the roof being torn off the bait shop and bar building, damage to the restaurant building and significant damage to the pier’s T-end decking.

Murphy said FEMA offered the city 75 percent of what was requested and that was due to questions about the scouring of the pier pilings that could not be definitively attributed to the hurricane. Scouring is erosion caused by moving water.

“I would have difficulty saying there was no scouring of the pilings prior to the hurricane,” Murphy said.

“If we challenge it, we go back to the steps we were in before – negotiating, getting engineers’ estimates and providing more information as to what we’re challenging,” Murphy said.

“If you accept this, they go on and complete the formalized offer. At that point, we could begin our construction. Until we get the formal offer back from FEMA, we can’t start that construction,” he added.

Murphy said it would take approximately 30 days to formalize the FEMA offer.

The state of Florida must also concur with the FEMA recommendation that also has to be presented to the Congressional Budget Committee because the funding request exceeds $1 million.

“They have to allocate the money to give us the resources to start the pier,” Murphy said.

“The bottom line is if you vote today to accept this offer, my estimate is that in the late October-early November time frame we could begin driving piles,” Murphy said, noting this would still keep the pier project on track for a December 2019 completion date.

Murphy originally anticipated construction beginning in September, but he and the commission have not yet selected a pier construction firm. After recently rejecting the first two bids received because the bids were too high, a modified request for proposals is supposed to be issued this week. Murphy said he expects the second round of construction bids to be submitted to the city by the end of September.

Murphy praised City Clerk LeAnne Addy for working on the FEMA funding for the past nine or 10 months.

“They lost all of our paperwork at one point. We’ve been showing records and we’ve been negotiating, and LeAnne has done a sterling job with bringing us to the point where we are today,” Murphy said.

Pier revenue sources

The mayor also presented the commission with a pier funding update. In addition to the FEMA money, the city has already secured $1.5 million in a Tourist Development Council recommendation for County Commission-approved resort tax revenues, $330,000 in County Commission-approved surplus beach concession revenues, $750,000 from the Florida Legislature and $650,000 from the city’s general fund.

Commissioner Brian Seymour noted the pier demolition cost approximately $750,000 and that leaves $4.4 million to build a new pier – a pier that includes a restaurant and bait shop at its T-end.

Murphy said the only amount listed in his revenue projections that has not been secured is the $500,000 he hopes to get from the pier tenant.

“I had always projected $500,000 from the tenant, whether it’s the current tenant or a new tenant,” he said.

The tenant’s contribution will be used for the interior buildout of the restaurant and bait shop.

Current pier tenant Mario Schoenfelder’s lease with the city expires in December 2020. He and Murphy have engaged in productive preliminary discussions but Schoenfelder had not yet committed to assisting with the pier funding and extending his lease. If Schoenfelder and the city cannot come to terms, a new tenant will be sought.

Related Coverage

Second pier construction RFP being issued

Pier construction permits issued

Pier construction bids rejected

Most Popular

More from Author

AMI community ‘rises up’ for River

ANNA MARIA – The Anna Maria Island commu­nity is coming out...

Holmes Beach ferry stop discussed

HOLMES BEACH – City elected officials are discussing with Manatee County...

Pedicini consulting for Satcher, Van Ostenbridge, Turner

MANATEE COUNTY – During a recent Supervisor of Elections debate, candidate...

Candidates Farrington, Satcher answer voter questions

MANATEE COUNTY – Manatee County Supervisor of Elections candidates Scott Farrington...

City presents 2024-25 budget

HOLMES BEACH – City leaders are working to keep property taxes as low as possible despite property values increasing an estimated 11.8%. To do that, they’re planning to keep the millage rate at 2.05 mills for the coming fiscal year and cut expenses from the proposed 2024-25...

Settlement reached in Piney Point litigation

PALMETTO - Prompted by a 2021 lawsuit by multiple conservation groups, the Florida Department of Environmental Protection (FDEP) has agreed to allow more oversight of discharges from the Piney Point phosphate facility. The settlement agreement also establishes enforceable limits on pollution discharged into Tampa Bay and provides for...

AMI community ‘rises up’ for River

ANNA MARIA – The Anna Maria Island commu­nity is coming out in sup­port of Mackenzie Morgan, Jonathan Anasis, their 3 1/2-month-old son, River Anasis, and their young daughter, Vayda Anasis. On July 13, the Rise Up for River Benefit: A Community Rally for Hope and Healing event took...

Holmes Beach ferry stop discussed

HOLMES BEACH – City elected officials are discussing with Manatee County tourism officials whether to add a Gulf Island Ferry stop in Holmes Beach. Currently, Manatee County’s contracted ferry service stops in downtown Bradenton, the Anna Maria City Pier and the Bradenton Beach Pier, with an additional stop...

Pedicini consulting for Satcher, Van Ostenbridge, Turner

MANATEE COUNTY – During a recent Supervisor of Elections debate, candidate James Satcher refused to acknowledge he’s us­ing Anthony Pedicini as his political consultant. Manatee County Commission candidates Kevin Van Ostenbridge and Ray Turner are also utilizing the campaign consulting services of Pedicini and his Tampa-based Strategic Image...

Government calendar

Anna Maria 10005 Gulf Drive For information, call 941-708-6130 Please visit www.cityofannamaria.com or contact city hall for more information. July 18, 1 p.m. – City Commission budget meeting July 18, 2 p.m. – City Commission meeting July 24, 9 a.m. – Planning and Zoning board meeting July 25, 5 p.m. – City Commission budget...

Beach Nutz

       

Events

Wednesday, July 17 One-on-one Tech Help, Island Branch Library, 5701 Marina Drive, Holmes Beach, 2 p.m. Sharks and rays conservation research, Island Branch Library, 5701 Marina Drive, Holmes Beach, 2 p.m. Thursday, July 18 One-on-one Tech Help, Island Branch Library, 5701 Marina Drive, Holmes Beach, 10 a.m. Wild About Wildlife, Island Branch...

Bargains on the beach

Realtor.com is part of my everyday life. I check it for new listings, sold listings, open houses and sometimes just to look at the pictures on what may be an otherwise slow day. Sometimes I even learn something I didn’t know, like their recent story about the 10...

Catch and release

Taking care when we release fish we don’t intend to keep has never been more important. While most anglers are aware that fish populations are vulnerable and not the endless resource we once thought them to be, shrinking habitats and fish populations make the process all the...

Second sea turtle nests in daytime

ANNA MARIA – More than 100 beachgoers saw an uncommon sight when a nesting loggerhead sea turtle laid her eggs during the day on June 26, the second daytime nesting in a week. Anna Maria Island Turtle Watch and Shorebird Monitoring volunteers posted photos and the following on...